30 ECS Installation of Town Wide Lighting Scheme PDF 462 KB
Minutes:
The Executive Member for
Environment and Finance & Governance and the Director Environment and
Community Services submitted a report for the Executive’s consideration. The
purpose of the report was to provide information on the Strategic Priority TOC
04 and request capital funding to enable its delivery.
Further to the successful
outcome relating to a number of buildings and key landmarks having external
lighting installed during 2020/21, a Strategic Priority had been agreed to
undertake a further programme of works during 2021/22. The programme included:
·
Town Hall / Municipal (North) - installation of
ground lights;
·
Bell Structure in town centre - ground and spot
lights;
·
Dock Clock Tower - installation of new lighting;
and
·
additional schemes - to
be agreed.
OPTIONS
As it was an agreed Strategic Priority, no other
decision was recommended.
ORDERED
That the requested £200,000 funding be approved to
allow the Strategic Priority to be actioned.
REASON
To ensure that the agreed Strategic Priority was
delivered within the stated timeline.