Issue - meetings

ECS Installation of Town Wide Lighting Scheme

Meeting: 13/07/2021 - Executive (Item 30)

30 ECS Installation of Town Wide Lighting Scheme pdf icon PDF 462 KB

Minutes:

The Executive Member for Environment and Finance & Governance and the Director Environment and Community Services submitted a report for the Executive’s consideration. The purpose of the report was to provide information on the Strategic Priority TOC 04 and request capital funding to enable its delivery.

 

Further to the successful outcome relating to a number of buildings and key landmarks having external lighting installed during 2020/21, a Strategic Priority had been agreed to undertake a further programme of works during 2021/22. The programme included:

·        Town Hall / Municipal (North) - installation of ground lights;

·        Bell Structure in town centre - ground and spot lights;

·        Dock Clock Tower - installation of new lighting; and

·        additional schemes - to be agreed.

 

OPTIONS

 

As it was an agreed Strategic Priority, no other decision was recommended.

 

ORDERED

 

That the requested £200,000 funding be approved to allow the Strategic Priority to be actioned.

 

REASON

 

To ensure that the agreed Strategic Priority was delivered within the stated timeline.