Venue: Council Chamber
Contact: Chris Lunn / Georgina Moore
No. | Item | ||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Declarations of Interest Minutes: There were
no declarations of interest received at this point in the meeting. |
|||||||||||||||||||||||||
Minutes - Executive - 21 September 2021 Minutes: The minutes of the Executive meeting held on 21 September 2021 were submitted and approved as a correct record. |
|||||||||||||||||||||||||
Youth Service: Overview of Progress, April 2021 - June 2021 (Quarter One) Minutes: An
amendment was tabled, the report was for information purposes only and was not
a key decision as the report had initially stipulated. The
Mayor and Lead Member for Children’s Social Care, Adult Social Care and Public Health
and the Director of Children’s Care submitted a report for the Executive’s
consideration. In June 2020, the Executive had granted approval to develop a
new Youth Service. The purpose of the report was to provide an update and
overview of the actions undertaken to develop the service. Following
approval from Executive in June 2020, a commissioning process commenced in July
2020 which invited bids from key voluntary and community sector organisations
to deliver Youth Services in partnership with the Council. Bids were identified
and prioritised on the basis of match funding, tangible community benefits,
youth work quality and outcomes with a specific focus on supporting young
people through Early Help, with key transition points and positive activities. The
work required identification of a number of youth centres across Middlesbrough,
which included community hubs and community centres. Allocated space had now
been identified for young people to access youth club activities. In addition,
spaces within buildings operated by the voluntary and community sector
organisations had also been identified. There
were three key elements to the Middlesbrough Youth Service model, including
universal, targeted and transition youth work. ·
Universal
Youth Work - delivered by The Linx Youth Project (see
further information at paragraph 4 of the submitted report) ·
Targeted
Youth Work - delivered by The Junction Foundation (see paragraph 5); and ·
Targeted
Transition Youth Work - delivered by Middlesbrough Football Club Foundation
(see paragraph 6). ORDERED That the overview of
progress made by the new Youth Service, which was given approval to be
established by Executive in June 2020, be noted. REASON It was important that
members of the Executive had a line of sight into the strategic and operational
work being undertaken in line with the Multi Agency Children’s Services
Improvement Action Plan 2020/21. |
|||||||||||||||||||||||||
Community Environmental Initiatives Additional documents: Minutes: The
Executive Member for Environment and Finance & Governance and the Director
of Environment and Community Services submitted a report for the Executive’s
consideration. The purpose of the report was to seek funding for ancillary equipment
and support to assist community and volunteer initiatives throughout
Middlesbrough. Community
groups and volunteers provided important additional environmental support to
the Council’s services and were increasingly valued. Their work was integral to
keeping Middlesbrough’s environment to a good standard and further encouraging
community participation. That was especially important as Middlesbrough moved
forward on its green agenda, striving to reach carbon neutrality and increase
the level of biodiversity in the Town. Providing
a supportive approach was leading to growing numbers of volunteers, who were
now networking with each other, leading to far reaching linked projects across
the town. As well as promoting the groups projects/initiatives via social
media, the Council could offer resource assistance by way of purchasing and
holding a stock of consumable supplies. That would enable those groups to
readily access tools, equipment and technical support to deliver initiatives,
which were of benefit to the environment, improving aesthetics and the
well-being of residents. Key
milestones to enable a measurement of performance against the intended
outcomes, included: ·
developing
a communications and marketing plan; ·
developing
an education plan to raise awareness of responsible waste management and
recycling; ·
developing
a plan to work with community groups and volunteers; and ·
providing continual support and provision of
equipment as required. OPTIONS To not supply
equipment, advice and support to community and volunteer groups was not an
option. It would have impacted on the Council’s green agenda and groups would
lose heart and faith in the Local Authority and eventually lose interest in
improving Middlesbrough. ORDERED That £150,000 revenue
(£50,000 per annum over three years) be approved to support community
involvement in wide reaching environmental Initiatives, to improve local
environmental standards across their communities and across Middlesbrough. REASON The proposed changes
planned to support the Council’s commitment to working with its communities and
partners to ensure that ideas and resources were shared to achieve joint goals.
It would also assist in meeting the Council’s aims detailed in its 2020-2023
Strategic Plan: ·
working with
communities and other public services to improve the lives of our residents; ·
working with
communities to improve local health and wellbeing, focusing in particular on
tackling obesity, poor mental health and substance misuse; and ·
working with local communities to redevelop Middlesbrough’s
disadvantaged estates, and introduce locality working with our partners,
placing services at the heart of communities. |
|||||||||||||||||||||||||
Council Tax Reduction Scheme 2022/23 Minutes: The
Executive Member for Environment and Finance & Governance and the Director
of Finance submitted a report for the Executive’s consideration. The purpose of
the report was to request permission to undertake a consultation (a requirement
of schedule 1A of the Local Government Finance Act 1992) with both the public
and the Major Precepting Authorities in respect of
proposed changes to the Council’s CTR Scheme with effect from 1 April 2022. It
was proposed that an alternative approach be taken from 2022/23, through the
redesign of the scheme to address all of the main areas highlighted in the
submitted report. Work
had been ongoing since early 2021 on a proposed alternative scheme, which was
now complete. Consultation now needed to be undertaken with the public and the
Major Precepting authorities. If accepted by the
Council, the proposed alternative scheme would take effect from 1 April 2022. The
proposed alternative scheme had a number of features, which were included at
paragraph 17 of the submitted report. Paragraph 18 provided details of how the
proposed alternative scheme planned to address the problems with the current
scheme. OPTIONS The alternative to
introducing a proposed alternative scheme for CTR from 2022/23 was to leave the
existing scheme in place. That would have been a short-term option; leading to
increasing costs of administration; and in the longer term, would have
significantly affected the collection of Council Tax and the effectiveness of
the scheme to support households within the Council’s area. Modelling (see table
below) had also been done on an alternative ‘income grid’ scheme with 85%
maximum support and 100% maximum support. The principles of that scheme were
exactly as described earlier in the report (see paragraph 17), however, given
weight to the options appraisal/rationale (Appendix C) those were not
recommended.
ORDERED That the commencement
of consultation on a maximum Council Tax Reduction Scheme of 90%, be approved,
with the following: ·
with Major
Preceptors on the proposed changes to the working age Council Tax Reduction
(CTR) scheme with effect from 1st April 2022 (as required by the Local
Government Finance Act 1992); and ·
with the public
on the proposed changes to the working age Council Tax Reduction (CTR) scheme
with effect from 1st April 2022 (as required by the Local Government Finance
Act 1992. REASON The proposed changes, planned to simplify a complicated scheme, further assist low income households and support the collection of council tax, whilst also fulfilling the obligations on local authorities to support the roll out of Universal Credit. ... view the full minutes text for item 21/61 |
|||||||||||||||||||||||||
Fountain Court Refurbishment and Fit-Out Budget Minutes: The
Executive Member for Regeneration, the Executive Member for Environment and
Finance & Governance, the Director of Regeneration and Culture and the
Director of Finance submitted a report for the Executive’s consideration. The
purpose of the report was to provide information on the building fit-out costs
for the Fountain Court refurbishment. The
Executive report, submitted on 16 March 2021, had highlighted that further due
diligence and survey work would be required to fully understand the costs of
the Fountain Court refurbishment. A
condition survey by Billinghurst George and Partners
had identified that although the building was in generally sound condition,
there were a number of expensive defects which required attention in the
short-to-medium term, such as full window replacement and an upgrade of the
Mechanical and Electrical (M&E) system. In
summary, the survey and design work had identified that £7m was required to refurbish
and fit out the building. That planned
to allow for the works identified to be addressed and a high-quality furniture
and fixtures fit out, which would incorporate the following: ·
new
furniture and fixtures which promoted the Council’s values and aligned with the
new blended working arrangements; ·
raised
access floors for services, needed for flexibility to future proof the
building; ·
replacement
and enlarged windows (the current windows were nearing the end of their life); ·
new
internal and external doors; ·
new
floor and ceiling finishes; ·
lift
refurbishment/replacement; ·
new
toilets and kitchen areas; ·
ICT
fibre connections and equipment; ·
signage; ·
drainage; ·
M&E
installation; and ·
consultant’s fees. In
the report to Executive on 16 March 2021, it had been anticipated that the cost
of the purchase and fit out of Fountain Court could be accommodated within the
fit out budget for One Centre Square, which was £5m. However, the report
acknowledged that detailed due diligence and survey work was required. The
due diligence and survey work had confirmed that a budget of £7m was
required. That included an 8%
contingency of £520,000, which was required to account for the market
fluctuations that were currently being experienced throughout the U.K. With
regard to utilising the £5m budget for One Centre Square, approximately
£600,000 had already been spent on survey, consultant works and purchasing the
furniture for the demonstration neighbourhood area, which left a budget of
£4.438m. The table, below paragraph 11
of the submitted report, provided a breakdown of the expenditure for Fountain
Court against that budget. In
summary, the total costs for the refurbishment and fit out of Fountain Court
were £7m, the available budget from One Centre Square was £4.438m so the
additional budget requested, when considering the £300,000 saving from the
demolition of the Civic Centre, was £4,138,596. OPTIONS The Council could: Do nothing: a)
The principle that the Council should relocate to
Fountain Court had been established by previous Executive direction. The building was not fit for purpose in its
current format and was unfurnished, hence a budget was required for its fit
out. Continue to proceed with the
remaining budget: b) The remaining budget (£4.438) minus ... view the full minutes text for item 21/62 |
|||||||||||||||||||||||||
Middlesbrough Development Company (MDC): Business Plan Update Additional documents: Minutes: The
Executive Member for Regeneration, the Executive Member for Environment and
Finance & Governance, the Director of Regeneration and Culture and the
Director of Finance submitted a report for the Executive’s consideration. The
purpose of the report was to provide a review of MDC’s activities over the past
year and to set out the priorities and anticipated expenditure for the next 12
months. As
it had now been 12 months since the approval of the MDC Strategic Plan, it was
considered an appropriate time for the company to provide the Shareholder with
a Business Plan Update, which was attached at Appendix 1 of the submitted
report. Paragraphs
8 to 11 of the submitted report provided a brief outline of progress since
September 2020. Construction
of the Boho Village and Newbridge
Court developments were both scheduled for completion by the end of September
2022 and work would now commence on the Empty Homes Partnership and CSI scheme.
In
addition, the Business Plan Update provided details of a number of pipeline
projects that MDC was developing in its capacity as a developer or development
enabler, which were being considered for delivery over the next year, subject
to Board and MBC Executive approval: a) Eyesore sites -
development of vacant and unsightly plots of land/buildings around the town. b) Middlehaven - developer or
development enabler for several vacant plots in or around the area. c) Former Captain Cook Pub
- development enabler to bring forward various options. The Council intended to
market the building and would, on completion of the remedial work in December
2021, seek interest from developers on a wide variety of proposals. d) Centre North East -
development enabler to facilitate a 200 unit apartment scheme. It
was anticipated that MDC would draw down between £10m and £15m in funding from
the Council over the next 12 months to progress the Boho
Village, Newbridge Court, Empty Homes Partnership and
CSI projects. ORDERED That the contents of
the MDC Business Plan Update, attached as Appendix 1, be noted. REASON The Shareholder Agreement
required MDC to provide the Council with a report setting out the progress of
the company in relation to the objectives and/or milestones set out in the
Business Plan. |
|||||||||||||||||||||||||
Centre Square Investment Opportunity - Part A Minutes: The
Executive Member for Regeneration, the Executive Member for Environment and
Finance & Governance, the Director of Regeneration and Culture and the
Director of Finance submitted a report for the Executive’s consideration. The
purpose of the report was to propose that to facilitate the development of 6
Centre Square, Middlesbrough Council provided Tees Valley Combined Authority
(TVCA) with:
i.
a
capital grant of £2,000,000; and
ii.
retained business rates in respect of 6 Centre
Square to TVCA, ceasing the earlier of a 15-year term, or, when the Government
changes the business rates mechanism. In
anticipation of relocating businesses and further inward investment enquiries, Ashall Developments secured planning approval for Building
6 Centre Square (see appendices 1 and 2 of the submitted report) in March 2021;
following which a revised masterplan (see appendix 3) for the remaining plots
received planning approval in July 2021.
Ashall Developments owned the site of the
former Melrose House Building and had cleared the site in preparation for
development of 6 Centre Square. Ashall led on the
development of phase one at Centre Square in Middlesbrough, demonstrating the
demand and quality for the facilities. In
May 2021, the Executive had approved a report entitled ‘Towns Fund and Future
High Streets Fund’, which had allocated £2m towards an “additional 40,000 sq.
ft. office”. Therefore, the proposals
within the submitted report provided an opportunity to realise the previously
agreed objective. TVCA
had also approved a sum in excess of four times that of the Council to provide
a full development budget for the construction of 6 Centre Square. TVCA aimed
to secure a long-term return on investment which could support the delivery of
major investments into the future. TVCA’s
investment was also subject to the transfer of retained business rates (49% of
the levy) outlined in Part B of the report. It should be noted that the
proposals contained within the report did not result in the Council losing
business rates income, as without the proposed funding package and resultant
construction of 6 Centre Square, there would be no such income to collect. OPTIONS
ORDERED 1.
That the information
contained in Part A of the report be noted. 2.
That the decision be
taken once all the financial or exempt information contained in Part B of the
report had been considered. REASON Economic Growth - In
addition to significant job retention, the prospective anchor tenant was
planning the creation of an additional 100-220 jobs in Middlesbrough. Costs - Provided ... view the full minutes text for item 21/64 |
|||||||||||||||||||||||||
Exclusion of the Press and Public To consider passing a Resolution Pursuant to Section 100A(4) Part 1 of the Local Government Act 1972 excluding the press and public from the meeting during consideration of the following item on the grounds that if present there would be disclosure to them of exempt information falling within paragraph 3 of Part 1 of Schedule 12A of the Act and the public interest in maintaining the exemption outweighs the public interest in disclosing the information. Minutes: The resolution to exclude the press and the public was agreed. |
|||||||||||||||||||||||||
EXEMPT - Centre Square Investment Opportunity - Part B Minutes: The Executive Member for
Regeneration, the Executive Member for Environment and Finance &
Governance, the Director of Regeneration and Culture and the Director of Finance
submitted a report for the Executive’s consideration. ORDERED That the recommendations of the report be approved. REASONS The decision
was supported by the following reason: For reasons
outlined in the report. |
|||||||||||||||||||||||||
The decision(s) will come into force after five working days following the day the decision(s) was published unless the decision becomes subject to the call in procedures. |