Venue: Mandela Room
Contact: Scott Bonner / Chris Lunn
No. | Item |
---|---|
Declarations of Interest Minutes: The Mayor
and Executive Members expressed thanks to the outgoing Executive Director of
Children’s Services for his hard work and dedication. Members commented that
services offered to Middlesbrough’s children and young people were in a
stronger position due to his tenure. There were
no declarations of interest received at this point in the meeting. |
|
Minutes - Executive - 11 June 2025 Minutes: The minutes of the Executive meeting held on 11 June 2025 were submitted and approved as a correct record. |
|
Progress against Continuous Improvement Plan Additional documents: Minutes: The Mayor submitted a report for
Executive Approval the purpose of which was to set out the expanded Continuous
Improvement Plan. The purpose of the plan was to ensure the Council could
articulate its ongoing commitment to Continuous Improvement and capture
activity that had been undertaken to deliver that commitment. In March 2025, Full Council considered the final reports of
both the Local Government Association (LGA) Corporate Peer Challenge team and
the Middlesbrough Independent Improvement Advisory Board (MIIAB). Both those
reports were hugely positive, recognising the improvements the Council had made
over the previous two years on its improvement journey. They also contained a series of recommendations, designed to
ensure the Council maintained an outcome focussed commitment to the principles
of the continuous improvement journey as it transitioned from a period of
intervention. A copy of the live Continuous Improvement Plan was appended
to the report and its status as of June 2025. Since the plan was agreed at Full
Council in March 2025, it had been expanded to reflect actions arising from the
External Assurance review undertaken by Grant Thornton as part of the
Exceptional Financial Support (EFS) application. The plan also included an
action arising from the Care Quality Commission inspection of Adult Social Care
services. There were currently 47 actions within the live plan. Of
those 47, 16 had been completed to date with the remaining in progress. This
was a live plan and a real commitment to continuous improvement. As such, even
where actions had been completed, their impact would continue to be tracked,
and further activity may need to be identified to ensure the actions had the
required impact and / or to ensure the Council continued to proactively address
the issues within the scope of the recommendations. The Mayor commented that a LGA peer
challenge follow up would be happening on the 12 and 13 November 2025. The Mayor also stated this matter would be part of his update to
the Overview and Scrutiny Board on 30 July 2025. OPTIONS The Council could choose to maintain multiple documents
capturing continuous improvement activity; however, this would be an
inefficient approach and would reduce Member’s ability to see a comprehensive
overview of the Council’s ongoing activity in relation to continuous
improvement. ORDERED that the updated Continuous Improvement Plan be
approved. AGREED that the progress made in delivering the
commitments within the Continuous Improvement Plan be noted. REASONS Having a Continuous Improvement Plan that captured all strategic Continuous Improvement activity, provided Members and Officers with a comprehensive overview of improvement activity within the organisation as part of a framework of assurance reports. Agreeing the revised content of the plan would ensure the Council was tracking this type of activity within one document. Further revisions to the live plan would be identified as necessary going forward. |
|
Middlesbrough Priorities Fund Minutes: The Mayor submitted a report for
Executive consideration. Proposals for funding from the Middlesbrough
Priorities Fund from Directorates were subject to completion of a pro-forma
outlining the proposal and detailing both which of the Council Plan objectives
and scheme criteria the proposal linked to. All proposals received from
Directorates were added to proposals received from Executive Members and were
collated into an overall ‘log’ spreadsheet which was assessed by the Mayor, with support from the Chief Executive, to determine
which were to progress for approval by Executive within each tranche and which
measures were either of lower priority or could be funded by other means. As signalled in the Executive report of 30 April 2025,
following this prioritisation the decision to implement the selected measures,
or not, would be taken by Executive. Once implemented the measures would be
tracked as part of the Council’s performance management framework, including
measurement of the impact and outcomes. As detailed in the Middlesbrough
Priorities Fund report to Executive on 30 April 2025, a Middlesbrough
Priorities Fund of £4.367m for 2025/26 only was established and approved by Full
Council on 19 February 2025 as part of the 2025/26 Revenue Budget, Medium Term
Financial Plan, and Council Tax setting report. The intention of the Fund was
to deliver high impact, one-off projects for the benefit of the communities in
Middlesbrough. A breakdown of the proposals submitted to date were detailed at
paragraphs 4.3 to 4.18 of the report. OPTIONS For no further proposals to be submitted. However, the
absence of any other proposals would mean that the Fund was not utilised to its
maximum potential provided for in the 2025/26 Budget approved by Council on 19
February 2025. ORDERED that the second tranche of proposals totalling
£1.310m as detailed in the report, be funded from the Middlesbrough Priorities
Fund. AGREED for it be noted if the proposed schemes included
in the report were approved, the unallocated balance remaining in the Fund
would be £2.142m. REASONS This would enable effective use of the Middlesbrough
Priorities Fund budget allocation set aside for 2025/26 and ensure Best Value
was obtained. |
|
Nunthorpe Community Centre – Next Steps Additional documents:
Minutes: The Executive Member for Development submitted a report for
Executive consideration the purpose of which sought Executive approval for the
proposed terms of the lease agreement and the commencement of construction of
the Community Centre. In 2024, Executive considered the Developing a new Nunthorpe
Community Facility report that provided an update on the progress on the
scheme. That report stated that an option appraisal had been undertaken, which
identified the most appropriate location for the Community Centre as being the
Council owned land adjacent to Nunthorpe Surgery on Stokesley Road. That report
further advised that a consortium led by Nunthorpe Parish Council with
Nunthorpe Community Council and the Nunthorpe Institute had been identified as
the preferred operator of the Community Centre following a formal selection
process. Since the appointment of the Management Consortium several
workshops had been held with Council officers to agree minor variations from
the layout that was used during the option appraisal process to identify the
preferred operator. The variations permitted were limited to maintain the
integrity of the option appraisal process. A detailed planning application was
submitted in March 2025 for the construction of a single-story building using
traditional methods of construction and associated external works comprising
car parking, footpaths and minimal landscaping. The building would have two
multi-purpose activity rooms, toilets, stores, kitchen and office space access
from a central circulation area. The proposed layout and elevation plans were
attached as Appendices one and two of the report. A detailed planning application was heard at Planning
Committee on 3 July 2025 and Members approved the development in line with the
officer recommendation. The Executive Member proposed an amendment to the recommendations
of the report, specifically recommendation C. The proposed amendment included
the Executive Member for Development as part of the delegation for variations
between Heads of Terms and the main lease. OPTIONS An option appraisal was previously undertaken, which
considered an alternative site for the Community Centre, but Stokesley Road was
identified as the preferred location. Expressions of interest were also sought to identify a
preferred management organisation. Three organisations submitted business
cases, which were scored against pre-determined scoring criteria, with the
consortium led by Nunthorpe Parish Council with Nunthorpe Community Council and
the Nunthorpe Institute being identified as the preferred operator. The scheme had now been submitted for Planning Approval,
and the tenders had been returned, but Executive could determine not to approve
the start of construction of the Community Centre. Failure to proceed with the construction of the Community
Facility would not meet the identified needs of the Nunthorpe community and
would be a reputational risk for the Council. ORDERED that Executive
|
|
Simpler Recycling – Legislation changes for Waste Streams Additional documents: Minutes: The Executive Member for Environment and Sustainability submitted a report for Executive consideration. The purpose of the report was to inform Executive of statutory changes to the household waste collection service, namely:
The report also informed Executive of the capital and
revenue funding required to implement the statutory services above and the
proposed funding mechanisms to provide this. The Council was required to commence with weekly food waste refuse collections by 31st March 2026. DEFRA had recently distributed capital funding to 251 local authorities. With Middlesbrough initially receiving funding from DEFRA for the purchase of receptacles (which were to be provided to households) and vehicles. The details of that funding were:
To meet the statutory food waste collection implementation
date of 31st March 2026, the Council had conducted a joint procurement exercise
with Redcar and Hartlepool Councils to purchase the required vehicles to ensure
best value and timely delivery. Due to expected timescales for vehicle deliveries the new
food waste service would commence implementation from 31 March 2026. Each household would be provided with the appropriate food
waste receptacles (an internal kitchen five litre caddy and an external 23
litre caddy). Larger households would be able to request to order more than one
external caddy. It was proposed that the Council would not charge residents for
additional and replacement / stolen caddies. It was proposed that the Council
would provide bin liners to residents free of charge for the internal caddies
for approximately one year. Members discussed the possibility of greater public
awareness on this matter. Members were advised that Environment Education
Officers were being recruited to undertake this and that members of the public
were free to attend any public information sessions that were taking place in
their local communities. In terms of food caddies being resistant to rodents,
it was clarified the food caddies were as robust as they could be and were used
in other Council areas. It was also stated that increased pest control would
help with this issue if the need arose. OPTIONS As the Council was statutorily required to comply with the DEFRA legislation no other options were put ... view the full minutes text for item 25/14 |
|
Proposed Changes to the Veritau Structure Additional documents: Minutes: The Executive Member for Finance submitted a report for Executive
consideration the purpose of which was to seek Executive approval to join a new
company, limited by guarantee, for the provision of internal audit and counter
fraud services, as per the attached business case at Appendix one of the report. The report also sought Executive’s approval for the payment
of a dividend by VTV, which would fund Middlesbrough’s subscription to VPS. The
previous company will then be wound up, as the other member Redcar and
Cleveland Borough Council has already moved over to the new arrangement. A
Director from the Council would need to be appointed to VPS in a similar way to
that already in place for governance purposes with VTV. A senior officer would
also need to be appointed to the VPS members’ committee. VTV operated as a Teckal company
(in accordance with the Public Contracts Regulations 2024 – as detailed in
paragraph 4.7 of the report) and was currently owned by Middlesbrough Council,
Redcar and Cleveland Borough Council (RCBC) and Veritau
Limited. Veritau Limited was jointly owned by North
Yorkshire Council (NYC) and the City of York Council (CYC) and was also a Teckal company. VTV provided internal audit and counter
fraud services to the Council, reporting the outcomes of this work to the
Leadership Management Team and Audit Committee. The work of VTV therefore
formed a key part of the Council’s overall framework of governance, control,
and risk management. The business case for the establishment of VPS was attached
as Appendix one of the report. The proposal was to join a new Teckal
compliant company, limited by guarantee, which would be jointly owned by the
councils who bought services from it (once the Council joined VPS, its members
would be NYC, CYC, RCBC, Leicester City Council, Cherwell District Council and
Middlesbrough Council). The formation and operation of the new company would
provide a sustainable business model, enabling VPS to continue growing and
allowing further member authorities to be admitted over time, as they bought
services from VPS, whilst protecting its Teckal
status. The Mayor sought, and received,
clarification that the Council still had the option to purchase more time that
the contract specified if necessary. OPTIONS Do Nothing – This was not considered to be viable as the
Council’s internal audit provider would not be allowed to grow its business,
otherwise it would become Teckal non-compliant under
the Procurement Act 2023. The Council would then need to re-procure the
services currently provided by Veritau or bring the
service in-house. As such, the alternative option was not viable, and the
proposal to join the new company, limited by guarantee, remained the most
appropriate solution to ensure continued Teckal
compliance and growth. This was the preferred route for both Veritau and the Council. ORDERED that Executive a)
Approve the membership of Veritau Public Sector Limited, a company limited by
guarantee, and the novation of the existing contract. b) Approve the payment of a dividend from Veritau ... view the full minutes text for item 25/15 |
|
Any other urgent items which in the opinion of the Chair, may be considered. Minutes: None. The decision(s) will come into force after five
working days following the day the decision(s) was/ were published unless the
decision(s) become subject to the call in procedures. |