Minutes:
A joint report of the Chief
Executive, Director of Finance and Director of Legal and Governance Services
was presented to provide the Committee with information in relation to the
planned reporting arrangements for delivery of the action plan that was agreed
by Council on 18 September 2023, in response to 11 statutory recommendations
made by the Council’s External Auditors Ernst & Young LLP (EY), exercising
their powers under Section 24, Schedule 7(2) of the Local Audit and
Accountability Act 2014.
The agreed recommendations and
supporting action plan that was agreed by Council on 18 September 2023 was
attached at Appendix 1 to the submitted report.
Progress against the action plan
would be reported to the Audit Committee as a standing item until delivery of
all actions was complete. Progress would
also be reported to the Independent Improvement Advisory Board (IIAB) that had
been established to oversee delivery of the Council’s Corporate Governance
Improvement Plan, as set out in the report to Council on 18 September 2023 that
outlined phase three of the Corporate Governance Improvement Plan.
The Chair of the IIAB and the
Council’s three statutory officers would also meet regularly with both the
External Auditor and the Department of Levelling Up, Housing and Committees in
separate meetings to discuss the Board’s independent view of the Council’s
progress against both the Section 24 action plan and phase three of the
Corporate Governance improvement Plan.
Progress against the CGIP would be reported as a standing item to each
ordinary meeting of full Council to maintain Member visibility.
Since the report was approved by
Council on 18 September 2023, two actions had been completed in line with their
target dates as follows:
1. A review of all existing purchasing cards had been
completed. A process was in place for reducing the number of cards across the
business and mandatory training had been developed for cardholders identified
moving forward. Training for the initial
cohort would be complete by November 2023 and then there would be a rolling
programme of training aligned with the assignment of cards going forward.
2. Pre-2021 ‘open’ exemptions had been identified and a full
analysis of would be reported to the Audit Committee in December within the
annual assurance report on
Procurement activity.
The first meeting of the
Independent Improvement Advisory Board (IIAB) had taken place on 2 October 2023
and another meeting was scheduled for November.
It was confirmed that a note of actions points had been made rather than
recorded minutes. This point was queried
by Members as it had been stated at a recent Council meeting that minutes would
be kept of IIAB meetings. The
Monitoring Officer confirmed the question had been raised at Council and agreed
that this position would be corrected.
The first meeting had set the
scene for the IIAB to understand Middlesbrough Council and discussion had also
taken place regarding engagement with Members.
An informal two-way conversation with Members was envisaged as well as
the formal process, and this was high up on the IIAB’s agenda.
The IIAB had been created by the
Head of Paid Service following discussions with the Department for Levelling
Up, Housing and Communities (DLUHC) and the External Auditor, EY, and was
required as part of the Council’s improvement journey. The appointments were made by the Head of
Paid Service, with the costs approved by Council.
It was noted that approximately
£750,000 was spent per month on purchasing cards and as part of a review the
number of cards in use had been reduced and more transactions were now going
through the purchasing system. The Head
of Procurement would be presenting a report to the next Audit Committee meeting
which would provide further detail on the review. It was highlighted that use of purchasing
cards had been reviewed previously, and it was explained that given the
Council’s current financial position, spending had to be restricted. In some cases VAT on transactions had not
been recouped.
It was clarified that the
mandatory Elearning would be delivered initially and
then on a cyclical basis to ensure that new employees would be included.
The target dates for action in
the report would have a detailed delivery plan and timeline and the Audit
Committee would receive regular updates.
Regarding Middlesbrough
Development Company (MDC), the Chair requested that the audited accounts, when
prepared, were submitted to the Audit Committee for information. It was confirmed there were currently two
Board Members and the Liquidators would appoint any further Board Members
required as part of the Company wind-up process.
AGREED as follows that
the:
1. information provided was received and noted.
2. proposed monitoring arrangements were approved.
3. audited accounts for Middlesbrough Development Company (MDC) would be submitted to the Audit Committee for
information when available.
4. Monitoring Officer would ascertain the minuting arrangements in relation to IIAB meetings and the process for the appointment of its Members.
Supporting documents: