Minutes:
A report of the Director of
Finance was presented, the purpose of which was to provide the Committee with
assurance in relation to the Council’s compliance with the Public Contract
Regulations 2015 specifically in relation to those contracts that had been awarded
subject to an exemption from the Council’s Contract Procedure Rules
(CPRs)/Standing Orders (SOs).
Exemptions were allowed under
specific circumstances as set out in the CPRs/SOs in exceptional circumstances,
details of which were provided at paragraph 4.7 below. The report provided a summary of the
Council’s activity in regard to exemptions submitted and approved under the
Council’s standing Order rule 5 (in accordance with the previous contract
procedure rules). To report on the current status of those exemptions and any
issues arising from their approval.
In compliance with the section 24
recommendation made by EY in August 2023, a full review of live contracts that
had been awarded subject to an exemption from CPRs has been undertaken. This identified the status of those contracts
and sought to provide assurance to the Committee that the Council’s procurement
practices were in accordance with Contract Procedure rules and compliant with
the Public Contract Regulations.
Details of the number of contracts
awarded subject to exemptions from CPRs since April 2021, and any contracts
awarded with exemptions prior to that date which were still live were included
in a table in the submitted report at paragraph 5.1. The table indicated that 4% of exemptions
received were in query by the Procurement service as a result of this
process. The detail concerning those
exemptions was outlined in Appendix 1 to the submitted report, along with the
issue and resulting actions. None of
the exemptions in query breached the Public Contract Regulations 2015 in terms
of the total value of expenditure exceeding the financial limits within the
regulations.
In addition, with regard to the
two contracts that were let subject to an exemption which had subsequently been
subject to a contract extension, the financial values had been checked and the
total amount fell below the Public Contracts Regulations 2015. The review concluded that all contracts that
had been awarded subject to an exemption were compliant with the financial
thresholds determined under the Public Contract regulations 2015. Members could
therefore be assured that the contract procedure rules in relation to letting
contracts subject to exemptions were robust and compliant with legislative
requirements.
Notwithstanding the assurance
provided by the review, the Procurement Service had sought to deliver further
improvement to strengthen the governance arrangements around procurement.
The contract procedures rules
were refreshed and approved by Council as part of the Constitution in September
2023. As a result, authorisation on
exemptions had been strengthened as follows:
• Requests for exemptions up to full contract value of £150,000 would be authorised by Head of Strategic Commissioning and Procurement.
• Request for exemptions in excess of £150,000 would be authorised by Head of Strategic Commissioning and Procurement, and the Director of Finance (Section 151 Officer).
• Request to
extend a contract that is subject to an exemption will be signed by Head of
Strategic Commissioning & Procurement, Director of Finance and Director of
Legal and Governance (Monitoring Officer).
The authorisation process assured
additional due diligence for any extension requests to an original
exemption. No extensions were permitted
if the contract values would exceed the thresholds set out in the Public
Contract Regulations. In addition the
guidance stipulated that exemptions should be for no more than two years,
unless there was a defined case which could demonstrate the value for money for
a longer time period.
A clear process had been
established for referencing, as prior to submission for signature a procurement
officer would explore all feasible options including the potential for call off
from frameworks, variation of existing contracts etc.
Mandatory training had been
provided to all budget holders in which exemptions had been covered, and the
case for exemption to be the exception, rather than the rule, had been
re-iterated to the staff base. Finally,
guidance on the staff intranet had been updated in regard to submission of
appropriate forms and associated guidance.
AGREED that the report was received and noted.
Supporting documents: