Minutes:
The Chair introduced the item and highlighted that
previously the Overview and Scrutiny Board had received the Executive Forward
Work Programme at each meeting for noting and proposed that the Board should
look at each item on the Programme in greater detail, going forward.
The Overview and Scrutiny Board had delegated powers to
manage the work of scrutiny and was able to undertake investigations itself or
delegate the work to individual scrutiny panels.
A key duty of OSB was to hold the Executive to account by
considering forthcoming decisions of the Executive and to decide whether
scrutiny could add value by considering any matter in advance of decisions
being made. Greater involvement in
pre-decision scrutiny would help to negate a non-executive member’s ability to
call-in a decision after it had been made.
Suggestions were sought from the Board regarding the
possible ways in which to have involvement in pre-decision scrutiny and the
following issues were raised:-
·
A Member commented that some of the items
contained on the Forward Work Programme had been made in May and, therefore, it
was too late for OSB to have any input into, whilst other items were due to be
decided upon in July so it was unlikely that a report had yet been compiled for
submission to Executive and it was queried at what stage OSB could become
involved. It was acknowledged that it
was difficult in terms of timing and background to the Forward Work Programme
was provided.
·
It was explained that any decisions which
involved spending £250,000 or more and/or affected two or more wards in
Middlesbrough was a key decision and must be placed on the Forward Work
Programme at least 28 days prior to a decision being made by the Executive. It was considered best practice to also add
non-key decisions to the Programme, as was the case in Middlesbrough. In terms of the report creation process,
there should be a 46-day lead in period prior to the report being submitted for
decision, so it would be possible to speak to Executive Members (and/or
relevant officers) prior to the decision being made. Once the Executive had made
a decision, it would become live within five days of the decision being
made but remained on the Forward Work Programme, therefore, there would always
be items on the programme where decisions had already taken place.
·
It was also highlighted that the Forward Work
Programme was available to view on the Council’s website, so Members could view
it at any time. Where the Board wished
to find out more about a particular item, the further ahead the decision was
due to be made, the better it would be in terms of having the opportunity to
have input.
·
In addition, it was suggested that the Chair and
Members may wish to agree to set up their own small task and finish groups to
look at specific issues and report back to the following meeting of OSB.
·
In summary, the Forward Work Programme could be
examined at any time by any Member but the format in which information was
requested and received may need to be tailored to each item depending on
timescales. Members would not
necessarily need to see a written report but may receive information about the
content of the report and a description of what the decision was about.
·
It was acknowledged that any dialogue between
the scrutiny and executive functions would require mutual trust and that whilst
scrutiny could have an input in terms of making recommendations, decisions were
ultimately made by the Executive.
·
A Member suggested recording the issues that the
Board looked at from the Forward Work Programme, including what information was
received, what the outcome of the decision was, whether the Board’s
intervention (if any) was affective, etc.
This could be reported to OSB on a twice-yearly basis to monitor
progress as monitoring progress of recommendations was something that needed to
be strengthened.
·
It was queried whether there was any way of
knowing when a written report was expected in relation to an item on the
Forward Work Programme. It was explained
that the Forward Work Programme was constantly being updated by the service
areas and that some decisions were moved back to later dates but generally a
final version of the report would be published five clear working days before
the date of the decision-making meeting.
AGREED that the content of the Forward Work Programme be noted and that for future meetings, each item on the programme would be considered to determine whether any further information was needed and what format this should take.
Supporting documents: