Minutes:
The Head of Finance and
Investment had produced a covering report to assist Members with the context
and understanding of the annual audit work, and the report that had been
submitted by the External Auditors. Auditors
from Forvis Mazars were in attendance to present
their annual report.
It was explained that assessment work in relation to the Council’s systems and arrangements for
securing value for money on the use of resources within the organisation had
been concluded. This covered the period
from 1 April 2023 to 31 March 2024. The
annual report presented the main findings on the audit work undertaken to date;
the findings of the report provided an updated assessment of the Council’s
Value for Money arrangements.
The report noted that the previous external auditor, Ernst & Young
LLP (EY), had issued statutory s24 recommendations for the 2022/22 and 2022/23
financial years in relation to the Council’s Value for Money arrangements in
August 2023. These were reported to
Council in September 2023 and addressed through a Corporate Governance and
Improvement Plan (CGIP) and s24 Action Plan.
Progress against these plans had been regularly reported to Council and
the Audit Committee.
Due to the change in the appointed external auditor, with effect from 1
April 2023, EY did not undertake a follow-up audit of the Council’s response to
its s24 recommendations, and therefore there would be no specific report made
to close down those recommendations by EY. The Forvis Mazars
report for 2023/24 therefore superseded the 2021/22 and 2022/23 report produced
by EY in relation to the assessment of the Council’s VFM arrangements.
The Forvis Mazars audit work had assessed the
Council’s arrangements in place during 2023/24 and, where appropriate,
considered the progress made up to the date of issuing the report. Forvis Mazars had
audited the Council’s VFM arrangements and identified weaknesses
(qualifications) in relation to all three elements of the audit assessment:
financial sustainability; governance and improving economy; and efficiency and
effectiveness. Recommendations were made
to the Council in respect of these weaknesses. However, no statutory s24 recommendations had
been issued as part of the report. Given the significance of the report, it would also be reported to the
next Council meeting on 15 January 2025.
A management response to the recommendations set out the progress made
during 2023/24 and to date in delivering improvement in the VFM arrangements.
The report also covered other matters that the external auditor felt
appropriate to report to the Committee as part of their work related to the
financial year 2023/24; this covered the opinion on the financial
statements. For the Council, this was
expected to be disclaimed in line with the accounts for 2021/22 and
2022/23. For the Teesside Pension Fund,
work was progressing well and was expected to be completed by the statutory
backstop date of 28 February 2025. The
report also gave information around significant risks, the control environment,
and audit fees for the financial year.
During discussion, several points were raised, as
follows:
·
A Member referred to governance
arrangements and queried whether there was sufficient capacity to deliver the
2024/25 audit on time. In response, it
was explained that interim agency staff were currently being retained to
support the permanent team. The interim
staff would remain in post beyond March 2025 to enable the accounts to be
audited by the backstop date. It was
indicated that a draft departmental structure and related reinvestment bid had
been produced, though permanent recruitment could not take place until the
Council budget had been considered.
However, work had already commenced in respect of the 2024/25
accounts. It was noted that there would
be challenge for the finance team to support the 2024/25 audit; additional
resources would be required. It was
highlighted that the interim Director of Finance would be leaving the authority
shortly; the post would be advertised on a permanent basis. A short discussion ensued in relation to the
high number of interim roles and the hopeful transference of these into
permanent positions in the future.
·
A Member referred to the
Council’s Transformation Programme and queried how this was progressing. In response, the Committee heard that
significant progress had been made within the last year, where enormous financial
challenge had needed to be met with the greatest of urgency. It was acknowledged, however, that there was
still significantly more work to do. The
importance of ensuring that Elected Members were fully informed and involved in
the Transformation Programme was highlighted; a training programme to assist
with this would be devised. The Director
of Finance advised that the draft 2025/26 budget report considered by Executive
on 4 December 2024 presented a balanced budget; the final financial settlement
amount was currently awaited. It was
felt that the savings identified were achievable and would meet the Medium Term
Financial Plan (MTFP). The Committee discussed exceptional financial support;
income management; and use of reserve funds.
·
A Member referred to the Q2
monitoring report and some savings that had yet to be realised; transformation
in Children’s Services and Adult Social Care was highlighted. A query was raised in relation to home to
school transport and the costs around that.
In response, it was indicated that £3m had been allocated to the SEND
budget for 2024/25 for this. A short
discussion ensued in relation to children in care and the management of complex
cases.
·
In response to a query regarding
Council Tax, additional housing and income generation, Members heard that this
was included in MTFP modelling / forecasting.
The Chair thanked the auditors
and officers for their reports and contributions to the meeting.
NOTED
Supporting documents: