Minutes:
The
Executive Member for Environment and the Director of Environment and Community
Services submitted a report for the Executive’s consideration. The purpose of
the report was to seek approval/endorsement for additional capital investment to
carry out principal and general inspections and repairs on the Council’s bridge
and structures assets.
The
Council, as a Highway Authority, was responsible for the repair and maintenance
of a large number of bridges and structures throughout Middlesbrough including
106 bridges, 65 culverts, 8 subways and underpasses, 3 gantries and 27
retaining walls.
Highways
England guidance stated that principal inspections should be carried out every
six years and the Council currently had 100 structures that required a
principal inspection and a further 98 structures that required a general
inspection. In addition to those inspections, critical works were required to 5
bridges and structures and general maintenance required to a further 22 bridges
and structures, which needed to be programmed for repairs. The cost estimates
to undertake those remediation works were far in excess of the Council’s
available annual Highway Maintenance Block Funding budgets.
The
total estimated cost, for inspections and repair works already identified, was
£4.54m in addition to the £400k already committed.
Future
years funding requirements, to complete the inspection programme and carry out
repairs identified, were included at Table 1 in the submitted report.
OPTIONS
Not approve the capital
investment in the highway infrastructure - That had not been recommended as not
carrying out the necessary inspection or repair works on the strategic route
network, and the A66 in particular, would have had a major impact on the local
network, with little resilience available for alternative routes through the
urban city centre of Middlesbrough. It
would have eventually led to severe disruption to the highway network and
significant additional cost for additional repair works that may have otherwise
been avoided with a programmed maintenance regime in place.
ORDERED
That £2.098m of
additional capital funding, for highways infrastructure investment, be approved
to enable the immediate inspection and repair works identified to be carried
out.
REASONS
The majority of the
works required were on structures either on, or over, the Council’s strategic
route network. When incidents occurred on the strategic network, requiring
works that affected the capacity of the routes such as closures of lanes, or whole
sections, then the impact on the network was significant. Completion of the
principal and general inspections, and carrying out the necessary repair works
already identified, would fulfil the Council’s statutory duty to maintain its
highway infrastructure, would have beneficial effects and improve the overall
highway network. In the event of a partial failure of any of the identified
structures, the best scenario would require weight limits to be enforced, lanes
closed and unplanned works to be carried out. In the worst case scenario, as an
alternative to planned structural repairs, would be structural failure of one
or more of structures with consequential sudden closures and chaotic dispersion
of traffic, (both private vehicles and HGVs), through the centre of
Middlesbrough. There was no available capacity in the local network to
accommodate that.
Supporting documents: