The
Public Rights of Way Officer will be in attendance to provide an update on
Flood Risk Management.
Recommendation: Panel to determine whether further information is required.
Minutes:
The
Public Rights of Way Officer gave an update on flood risk management.
Following
major floods in 2007, the Pitt Report recommended that Local Authorities’
scrutiny committees should receive an annual summary of actions taken locally
to manage flood risk.
World
weather patterns were changing and it was essential that authorities responded
by planning ahead and increasing resilience to the changing demands of climate
change. Potential risks of climate
change included wetter winters, hotter summers and rising sea levels. Extreme weather events were likely to happen
more frequently and with more intense isolated downpours during summer that
could lead to more regular flooding.
There was therefore an increasing need for authorities and the public to
adapt and prepare for these conditions.
Middlesbrough’s
drainage system was extensive and complex in nature, comprising open and
culverted watercourses and a surface water/combined sewerage system. Parts of the highway drainage network dated
back to the early 1900s and little was currently known about its capacity and
condition and it was therefore uncertain how it would cope with increased
rainfall. Over the years there had been
increased flooding from the highway drainage network due to reduced capacity
within the road gullies and the drainage network. Ground water levels were rising as a result
of increased rain during the summer, thus reducing the ground’s capacity to
take the increasing amount of rainfall in the winter and resulted in greater
instance of surface water runoff.
The
Environment Agency (EA) had produced a map showing areas where it predicted
surface water would collect in Middlesbrough when there was a one in one
hundred year storm event.
Flooding
could come from a variety of sources including surface water run-off, ordinary
watercourses and surcharging sewers.
Surface water flooding occurred when intense rainfall, often of short
duration, was unable to permeate into the ground or enter the drainage systems
quickly enough, resulting in ponding or overland flows. This could cause considerable problems in
urban areas such as Middlesbrough. Middlesbrough
was one of the worst areas affected by surface water flooding in the north east
due to its urban nature and the presence of clay close to the surface.
The
Council worked closely with Northumbrian Water (NWL) on Integrated Drainage
Studies. Middlesbrough had four or five
drainage areas which were catchment areas where the water fell and was
collected into specific drains. The
strategic studies highlighted and prioritised the areas of greatest risk from
flooding within each of the catchment areas.
Stage 1 of a study focussed on the collection, collation, analysis and
prioritisation of information to identify areas of high risk from
flooding. Stage 2 focussed on
identifying opportunities within the top three or four high risk areas to
reduce or prevent flooding. The results
of the studies provided all the information required to apply to the EA for
funding for flood management schemes.
Currently
there was one study in progress which was in Middlesbrough East. Stage 1 was undertaken in 2018 and identified
10 flood risk areas. Three of those
areas were taken to Stage 2 and that study began in 2019 and was predicted to
be completed by June 2021.
Funding
could be achieved either through the EA and central government funding or
through local levy which was collected through council tax. Funding could be used for studies or for
ground work. The EA’s six year
programme, called the ‘Medium Term Plan’ ended in 2020. Middlesbrough had received funding for
schemes in Saltersgill, Ormesby Hall are and Cornwall Close.
The
Council now had to submit schemes to be included the next six year programme –
the ‘Long Term Plan’ for Flood Defence Grant in Aid (FDGiA).
The
schemes submitted by Middlesbrough were:
Gresham
Road and Newport.
Lawnswood
Road.
Barrington
Crescent.
Pallister.
Berwick
Hills.
Thornfield
Road.
Whinney
Banks.
Connaught
Road, Nunthorpe.
Shevington
Grove, Marton.
It
was confirmed that funding would be forthcoming to investigate the potential
benefits of all the schemes. Four of
the schemes; Lawnswood Road, Barrington Crescent, Pallister and Berwick Hills,
were within the East Middlesbrough study area.
These nine schemes would potentially protect 588 homes.
The Council continued to investigate the highway
drainage system, which had not been previously recorded or mapped. The aim was to increase knowledge of the
system and the interactions with sewers and watercourses. The system could then be repaired and
cleansed as appropriate. The Council
undertook regular maintenance of the gullies and worked to resolve any flooding
issues when the occurred.
The Council also continued to work with Developers
to ensure that Sustainable Drainage (SuDs) techniques were part of all major
developments. In partnership with the
Planning Department there was a draft Green Blue Infrastructure Plan that
looked at the whole of Middlesbrough, what green spaces there were and what
benefits could be brought to those areas.
Middlesbrough needed the green spaces to be able to hold water and also
undertake schemes to hold water back.
The Council also considered how the same areas could be utilised, for
example schools having ponds in their grounds.
A detailed update was provided on progress with
current schemes which included:
Saltersgill Fields - creation of ponds and scrapes
and a bund to better protect 306 properties.
Although slightly delayed due to the covid-19 pandemic and also
unprecedented rainfall, the scheme was completed in November 2020, on budget,
and with additional benefits. The
additional benefits included the installation of a footpath across the fields
and a knee rail around the overflow car park to prevent vehicular access to the
fields. In response to a query it was
acknowledged that the knee rail was not effective against motorcycles but it
did prevent other vehicles from accessing the fields.
Cornwall Close – creation of a bund and deflection
of surface water into highway drains to provide flood risk reduction to 3
properties. Funding had been approved
and planning permission would be submitted soon and construction would begin
later this year.
Ormesby High Street – creation of a bund, flood
defence wall and some property level protection. This revised scheme covered two flow paths
with potentially 100 homes better protected compared to the original 18. The EA had recently undertaken works to the
trash screen on the culvert to allow water to flow through more quickly.
Another major scheme during the last year was the
Marton West Beck Scheme which was managed by the EA in partnership with
Middlesbrough Council. The aim of this
scheme was to reduce the amount of water coming downstream so that the lower
stream culverts could cope. A series of
bunds had been created in Albert Park to hold water back, the height of the
wall at the side of the Park had been raised, and the lake was now utilised as
a water storage area. The trash screen
at the north east end of Albert Park had also been improved with a lateral
screen added. Work had also been
undertaken at Borough Road where the flood walls had been improved. A series of bunds had also been created
upstream, near to Nature’s World, which would hold the water back and release
it gradually into the beck. The scheme
on target to be completed by March 2021.
A Member raised concern in relation to the work at
Nature’s World and drainage area that had been formed but did not appear to be
holding water. The Officer explained
that there were different types of SuDs.
Ponds would hold water all the time and release it gradually, whereas
bunds would only fill up when there was a one in one hundred years type storm
event.
Responding to a query, the Officer explained that
in relation to new housing developments, he provided comment on all planning
applications in relation to the design of flood management. All developers had a legal responsibility to
ensure that all water was managed on site.
The
Chair thanked the Officer for his presentation.
AGREED that the information provided was received and noted.