Minutes:
The
Director of Regeneration submitted a report to introduce a Toucan Crossing on Stainton Way, immediately to
the west of the Gables Roundabout, in order to provide a safe crossing point for
children travelling between Hemlington Grange and The
King’s Academy in Coulby Newham.
The report required a decisions as the
proposals would impact upon the road safety of residents, school age children
in particular, in the Hemlington and Stainton &
Thornton wards. Approval would continue
to ensure that the proposals are aligned with the Councils ambitions and
objectives.
The report outlined that following its
allocation for housing in the 2014 Middlesbrough Housing Local Plan, planning
approval for the Hemlington Grange development was
granted in April 2016. Comprising well
over a thousand dwellings, it is the largest residential development currently
under construction in the Borough.
Because of the way that construction of Hemlington Grange has been phased, all of the 300 or so
dwellings built and occupied to date are located towards the eastern end of the
development, in an area to the south of Stainton Way and to the west of B1365 Stokesley Road. As
most of the local facilities serving Hemlington
Grange are located in Coulby Newham, residents
travelling on foot or by cycle to reach those facilities have to cross Stokesley Road and/or Stainton Way when doing so.
The plan attached at Appendix 1 to the
report showed the existing and proposed pedestrian and cycle links serving Hemlington Grange.
At present, the only footpath route between Hemlington
Grange and Coulby Newham obliges pedestrians to cross
Stokesley Road by means of an uncontrolled crossing
point located roughly midway between its junctions with Stainton Way and Hemlington Grange Way, and then proceed through the
Ridgeway industrial estate to reach the footpath/cycleway linking the area of Coulby Newham to the south of Stainton Way with the
district centre. There are no existing cycle
routes linking Hemlington Grange and Coulby Newham.
To address this situation, approval was
granted for a new footpath/cycleway link – connecting Hemlington
Grange with the existing pedestrian and cycle network serving the area of Coulby Newham to the south of Stainton Way. Once in place, this link will complete a
continuous, safe and direct pedestrian and cycle route connecting Hemlington Grange with many of the local education,
employment and leisure facilities in Coulby Newham.
The new link will also connect Hemlington Grange with The King’s Academy. Many of these students currently travel from Hemlington Grange to The King’s Academy via the existing
footpath on the western side of Stokesley Road,
crossing Stainton Way immediately to the west of the Gables Roundabout and then
completing their journey via the existing footpath/cycleway route on the north
side of Stainton Way, crossing B1365 Hemlington Lane
at the staggered Toucan Crossing that was introduced in 2015.
This issue has been raised by Members
representing both the Hemlington and the Stainton
& Thornton Wards, as well as by residents of Hemlington
Grange whose children attend The King’s Academy.
The cost of the crossing and
the associated footpath/cycleway link is estimated to be in the region of
£100,000. However, the figure will be
refined during the scheme design process. All costs
associated with the scheme will be met from that part of the capital
receipt for the Hemlington Grange development
allocated for the provision of sustainable transport links. The total sum allocated for such works is
£885,000, as approved by Executive in August 2013.
Given the current concerns regarding
pedestrian safety, it was intended to deliver the proposed scheme as swiftly as
possible, with a view to the new crossing coming into operation before the
start of the 2021/22 academic year in September. The indicative implementation timetable is
set out in the table below:
Task |
Timescale |
Executive Member Approval |
March 2021 |
Preliminary Design |
March to April 2021 |
Consultation |
April to May 2021 |
Detailed Design |
May to June 2021 |
Procurement |
June to July 2021 |
Construction |
July to August 2021 |
The report outlined that the actual delivery
programme will be refined and developed as work to implement the scheme
progresses.
Options
Other
potential decisions and why these have not been recommended
The other potential decisions that have not
been recommended include:
a) Do nothing - this is not recommended as
it will not allow the residents of the aforementioned wards safely access the
Kings Academy. A road traffic accident
occurred in late 2020 on Stainton Way and further highlighted the need for the
Council to install a safe crossing point immediately. The growth of Hemlington
Grange means that the demand for a controlled crossing facility at this
location will continue to increase in future years.
b) Re-assessing the project proposals –
this is not recommended, as the lack of any pedestrian and cycle crossing
facilities at the appropriate section of Stainton Way, immediately to the west
of the Gables Roundabout means that there is no safe crossing point for
children travelling between Hemlington Grange and The
King’s Academy.
c)
Approve the proposal and deliver the proposed
Toucan Crossing. Work will then commence
to detailed design of the proposals and commence construction thereafter.
The Chair formally thanked the Ward
Councillors and residents involved in bringing forward concerns which led to
this decision being made.
ORDERED
a)
That the proposed Toucan Crossing on
Stainton Way be approved in principle;
b)
That the cost of the crossing be met
from that part of the capital receipt for the Hemlington
Grange development allocated for the provision of sustainable transport links;
and
c)
Work to deliver the scheme commences
immediately, with a view to the new crossing coming into operation before the
start of the 2021/22 academic year.
REASONS
The
decisions were supported by the following reasons:
a)
This would allow
prudent allocation of capital receipt funding for the Hemlington
Grange Development site, to install a Toucan Crossing on Stainton Way to allow
for a safe crossing for residents of the Hemlington
and Stainton & Thornton wards to the west of Gables Roundabout on the
B1365.
b)
This is a much
more direct route, for which demand will inevitably increase as the number of
properties in Hemlington Grange continues to
grow. However, the lack of any
pedestrian or cycle crossing facilities on this section of Stainton Way means
that the potential for collisions to occur (as it did in December 2020), is
also likely to increase unless prompt action is taken.
Supporting documents: