Schedule -
Page 11
Item 1 -
Land Adjacent to Ayresome Gardens (Update Report) - Page 13
Item 1 -
Background Paper - Committee Report (17 December 2021) - Page 19
Item 2 -
Unit 5, Captain Cook Square - Page 35
Minutes:
The Head of Planning submitted
plans deposited as applications to develop land under the Town and Country
Planning Act 1990.
20/0374/FUL Erection of part-three, part-four storey residential
accommodation comprising 74no. beds for student
accommodation (sui generis) at Land Adjacent to Ayresome Gardens, Middlesbrough
TS1 4QN for Mr A Mushtaq (UPDATE REPORT)
The Development
Control Manager advised that the above application had been
identified as requiring a site visit by Members of the
Planning and Development Committee.
Accordingly, a site visit had been
held on the morning prior to the meeting.
Full details of the planning
application and the plan status were outlined in the original officer
report. The report contained a detailed
analysis of the application and analysed relevant policies from the National
Planning Policy Framework and the Local Development Framework.
Members were advised that the
application site had been granted planning permission for a similar use in
2016. Through planning permission
M/FP/0374/16/P, consent had been granted for the construction of a
part-two/part-three storey building, with a brick/block with render external
appearance, accommodating 72 student beds.
Although the development had not been constructed, pre-commencement
conditions had been discharged and groundworks had commenced. That meant the 2016 permission had a
technical commencement and was extant, and could be built out any time. Therefore, it was considered that the
principle of a development for student accommodation on the site, had been
established.
The application had initially been
submitted to the Planning and Development Committee meeting held on 17 December
2021 for consideration. The Development
Control Manager advised that the purpose of the update report was to inform the Committee
of the responses received from the Agent and Applicant following the issues
raised by Members at the previous meeting.
They included points of clarification and revised plans relating to the
following matters:
-
The
potential impact on the trees in the park including their influence on the
likely residential amenities of future occupiers;
-
The
proposed parking arrangements to facilitate drop-offs and pick-ups of students;
-
Waste
store arrangements and functionality; and
-
The
practically of the bicycle store arrangements.
In addition to the above, the report also covered
the issues of the access to the alleyway, the installation of alleygates, and
other permissions required to access the site.
Notwithstanding the submission of additional
information as discussed in the report, it remained the officer recommendation
to refuse planning permission.
The scheme had been confirmed by the Applicant as
now being for student use only rather than including potential use as a House
in Multiple Occupation (HMO). The number
of beds had also been reduced from 75 to 74.
Regarding trees, the footprint of the proposed
building would be close to the northern boundary with Ayresome Gardens, where a
number of trees were situated along the boundary. The distance between the principal elevation
and the trees was approximately two metres, which included four mature trees
and many saplings that had recently been planted.
In the event of approval, it was considered that
the construction of the building would have two principal implications. Although the trees could be retained
alongside the development, it was likely that the construction works would have
lasting harmful impacts on their structural integrity and the general health
and conditions of the trees placing a burden for their future removal. Additionally, any trees sought to be retained
were likely to have significant impacts on the general living conditions of
certain rooms. Given the proximity of
the trees, it was likely that many room windows would be severely obscured by
the canopies of the trees, and therefore require constant maintenance or face
significant pressure for lopping or felling on a regular basis.
The report noted that if Members were minded to
approve the application, officers would recommend that all of the trees
adjacent to the northern boundary be removed and replacements of an equivalent
or suitable quality be planted in an appropriate location, which may be away
from the locality. As it was a need
associated with the development of the site, it was considered appropriate for
the development of the site to bear that cost.
To secure that, a Section 106 legal agreement would need to be entered
into between the Council and the developer.
With regards to parking arrangements, officers had
previously raised concerns over the lack of parking spaces within the site to
allow the drop-off and pick-up of students at the start and end of term. Members of the Committee shared those
concerns and, subsequently, a revised scheme had been submitted showing four
parking spaces within the boundary of the application site. It was noted that the footprint at the
eastern end of the building had been modified in order to achieve four standard
parking spaces, with the laundry room and the stairwell being reorganised.
Although four vehicle parking spaces had been
introduced, their position and arrangement raised concerns as to whether two of
the spaces could be reasonably used given the limited width of the alleyway,
which would be required for reversing manoeuvres.
Regarding the waste store, the original officer
report considered there to be a shortfall in the waste store provision, as
sufficient information had not been provided as to the arrangements for storage
and collection of waste from the proposals.
The original drawings showed one waste store that accommodated four
Eurobin style bins, which was considered an under provision for the size of the
development and the number of future occupiers.
Revised drawings had been submitted showing two
proposed waste stores with a capacity for accommodating ten Eurostyle
bins. In addition, roller shutter-style
doors had been introduced on the rear elevation to enable bins to be taken out
into the alleyway for collection. It had
also been confirmed that a private contractor would be employed to carry out
collections up to twice a week. It was
assumed that the private collection of bins would include the collection from
the premises rather than requiring the bins to be pulled to the highway, which
would be a matter for the management of the premises. Should any bins be left out or obstruct the
adopted alleyway, that would be a matter for the
Council’s Highways Enforcement Team.
Based on the revised drawings and additional
information, the waste storage and collection arrangements were considered to
be acceptable.
The Development Control
Manager advised that there had been uncertainty over cycle parking provisions
for the development and the applicant had sought to confirm the storage
arrangements as being individual cycle lockers, located on each floor of the
development, within the corridors. The Development Control Manager
advised that locker storage was considered to be ok in principle but that the
provision of cycle storage on the upper floors was considered unsuitable as it
required bikes to be brought through the building, along its corridors,
upstairs or up in lifts which represented a poor offer, likely to limit the
take up and use of cycles for a development with zero parking for its
occupants.
Regarding alleygates and access matters, at the 17
December 2021 meeting officers brought the issue of the alleygates to the
attention of Members. The following
information was provided for clarity on those matters discussed at the meeting.
The Council’s planning officers had been advised
from the other internal departments that although the alleygates had been
installed within the alleyway, that was without the formal consent or required
legal mechanisms of the authority.
Equally, again whilst not a planning matter, it was stated on behalf of
the Applicant at December’s meeting that all relevant permissions to gain
access across Council land had been asked for and given. The Council’s Land and Property team had
advised that there were no legal agreements in place between the Council and
Applicant regarding access, which had been brought to the Applicant’s
attention. The report indicated that,
for clarity, those were matters which fell outside of planning considerations
and should therefore not influence the planning decision, although would need
to be addressed by the Applicant/Developer were permission to be granted.
Regarding other matters, as noted in the Parking
Arrangements section, the footprint of the building had been altered in order
to provide the four parking bays. That
had resulted in some changes to the room arrangements, the main ones being as
follows:
-
Communal
lounge areas from the ground, first and second floors had been reduced from 2
to 1;
-
The
laundry/store areas on each floor had been removed, with a smaller laundry area
being introduced at the eastern end; and
-
The
stairwell at the eastern end of the building had been repositioned 90 degrees
with access being achieved at the side elevation.
The above matters of contention, along with the
original officer concerns regarding the design and scale of the building,
remained considerable issues and the recommendation remained to be to refuse
consent in line with the following reasons:
·
The proposed development would be significantly harmful to the
living conditions of the residential occupiers of the terraced houses to the
south along Crescent Road. That was owing to the proximity of the proposed
development, the four-storey height in particular, to the rear elevations and
gardens of the dwellings along Crescent Road;
·
The lack of adequate parking and servicing arrangements would lead
to a displacement of such activities onto the adjacent public highway. The
surrounding public highway was considered to be highly constrained in terms of
width and parking demands. The impact of
those activities onto the public highway would interfere with the free flow of
traffic along Crescent Road, cause obstruction of the highway and would be
detrimental to highway safety; and
·
The proposed development by virtue of its size, design and
appearance would adversely affect the character and appearance of the Albert
Park and Linthorpe Road Conservation Area, with particular reference to but not
exclusively, in relation to the traditional terraced properties immediate south
of the site. In the absence of any
significant public benefit, it was considered that the proposals would not
complement any nearby heritage assets within Conservation Area.
Although the revised drawings were considered to
reasonably address the issue of the waste storage and collection, it was the
officer view that the bicycle stores and their associated impracticality, as
well as the cramped parking arrangements remained to be unacceptable as they
represented poor design, and whilst the matter of tree removal, replacements
and replanting could be addressed by a legal agreement, it did not overcome the
other matters.
A Member raised a query regarding
bicycle access to the proposed building.
The Development Control Manager advised that it would be possible to
take bicycles into the building via the front, side or rear doors. It was commented that the rear alleyway was
narrow and that the presence of vehicles alongside bicycles would create
further traffic issues.
A Member raised concerns regarding
the mature trees that would need to be removed and subsequently replaced. In addition, concerns were also raised
regarding the entrance onto Ayresome Gardens; bicycles; the narrowness of the
rear alleyway; and the difficulties that would be encountered in accessing the
proposed building. A further Member
reiterated those concerns, commenting that with increased traffic it would have
been difficult for the minibus to manoeuvre during the morning’s site visit.
The Land Owner was appointed to
address the committee, in support of the application.
In summary, the Land Owner
distributed some additional notes to the Committee and advised that:
·
In referencing an email from an officer in the Highways
department, the alleyway was a designated highway and the correct procedures
had been followed in relation to obtaining permissions for alleygates and
access;
·
Correspondence had been undertaken with officers in relation to
the storage of bicycles on each floor;
·
Correspondence had been undertaken with officers in relation to
trees and the acceptance of a section 106 agreement for the planting of
replacements (the Land Owner felt that the trees were end of life and he would
be willing to plant replacement trees on a fourfold basis);
·
Similar successful developments had been achieved in other areas
with high student populations, including Newcastle upon Tyne;
·
Correspondence and meetings had taken place with officers in
relation to the front entrance from Ayresome Gardens; and
·
Correspondence and meetings had taken place with officers in
relation to the design and scale of the proposed building.
In response, the Development
Control Manager made the following points:
·
Regarding the issue of trees, a section 106 agreement would need
to be established; replanting trees on a fourfold basis was not an
agreement. Reference was made to the
proposed building being in a conservation area and therefore sufficient value
given to the trees’ presence;
·
As advised by appropriate officers, there was no legal agreement
in place for the alleygates to be in situ.
The Development Control Manager was not aware of any further
correspondence in relation to that matter;
·
With regards to the student population, that was part of the
Applicant’s case; information provided was neither right nor wrong, but it was
explained that developments undertaken in other student towns and cities were
not relevant to Middlesbrough; and
·
Information in relation to meetings that had been held with
planning officers was provided. Although
it was felt that the revised design for the building was an improvement to that
originally submitted, in terms of scale that had been increased and therefore
needed to be justified. It was explained
that all matters discussed with planning officers at the pre-determination
stage were caveated that any increase in scale would need to demonstrate it
could be reasonably accommodated.
A Member raised a query regarding
ownership of the rear alleygates. In
response, the Transport Development Engineer advised that the rear alleyway was
publicly maintained and therefore the Local Authority was responsible for it. It was unclear as to what agreements, if any,
were currently in place in terms of the presence of the gates. The Local Authority had the power to have
alleygates removed if a legal and lawful process as to their installation had
not been followed.
A Member raised concerns regarding
the removal of mature trees; accessibility problems owing to the size of the
alleyway; and a lack of parking provision.
It was felt to be a positive scheme, but its locality was
questionable. In response to those
comments, the Land Owner indicated that bicycles were intended to be taken out
of the building’s rear entrance, as opposed to the front. A larger than average lift would be installed
to help facilitate that. Reference was
made to communications that had taken place with GINGER to have the development
nominated as a hub for E-scooters. With
regards to parking provision and rear access, it was explained that the
previous scheme had four parking bays, which had now been reinstated. The Land Owner had carried-out testing with
two large vehicles and determined no issues.
A discussion ensued in relation to
the proposed access to the front of the building. A Member commented that the access could
potentially be lost if an event was to be held at Ayresome Gardens. In response, the Land Owner indicated that
that was legally common space and was under the ownership of Middlesbrough
Council. Legal advice sought by the
Applicant had indicated that although agreements would be required, that would
not necessarily cause any issues. The
Council’s Solicitor referred to the correspondence that the Land Owner had
submitted prior to his presentation and explained that none of the information
contained within it was legally binding as being in agreement with the Council,
as all matters discussed would need to be agreed by the Planning and
Development Committee or Legal Services; the Land Owner accepted the point.
A Member made reference to the rear
alleyway and commented that a one-way system was not currently in place. It was felt that issues would be experienced
if two vehicles entered the alleyway at the same time, particularly as there
was no turning circle available. That
could also pose further safety problems given the number of students that would
be on site. Consideration was given to
access for emergency vehicles and also in the event of a vehicle breaking
down. In response, the Land Owner
explained that students would enter the development via the front
entrance. In response to a request for
the four parking bays to be reinstated for pick-up and drop-off purposes, that
had been agreed; no turning area was ever available for use. With regards to a one-way system, the Land
Owner explained that he would be agreeable to the implementation of that.
Two Ward Councillors were appointed
to address the Committee.
In summary, the Ward Councillors
advised that:
·
Ayresome Primary School was currently accessed via Ayresome
Gardens and therefore it was difficult to see how the proposed scheme would
differ;
·
Several of the trees currently on the site had fallen down and
therefore it was felt accurate to define them as being end of life;
·
It was common practice in Newport for motorbikes and mobility
scooters to be kept in yards and taken out through alleyways;
·
The proposed scheme would provide high-quality accommodation for
students, which would be the next best thing to the previously-planned student
village;
·
Implementation of a one-way system was supported, but to all
alleyways if possible;
·
The proposed modern building would revitalise the Ward and provide
a quality investment for the area;
·
The Land Owner was prepared to work with the Council to develop
the scheme, which was an excellent offer; and
·
There had previously been issues with fly tipping, vermin and
needles on the site – it was felt that the development would help prevent that.
Members discussed the application
and considered the issues that had been raised, including: the potential
implementation of a one-way system; the design of the proposed building;
parking provision; the current condition of the area; accessibility to the
building; and removal of the trees. In
response to an enquiry from the Head of Planning, a Member commented that
sufficient parking in their view would be four accessible parking spaces.
The Transport Development Engineer
explained to the Committee that there was a separate legal process involved in
the implementation of a Traffic Regulation Order (one-way system). Therefore, if Members were minded to approve
the application on condition that a Traffic Regulation Order be initiated,
there was no certainty that that would be achieved.
During discussion, it was commented
that although the scheme had a specific footprint, e.g. buildings next door,
rear alleyway in situ, etc., Members still held some reservations in relation to
trees; the implementation of a Traffic Regulation Order; and parking
provision. Those aspects would require
further clarification/information/determination from appropriate officers. The Transport Development Engineer made
reference to the refuse collection strategy and indicated that the collection
point was significantly greater than the usually expected allocation of
20m. In addition, if the refuse
collection frequency were to be increased, from one to two collections per
week, there would be a refuse vehicle on Crescent Road more often. Consideration was also given to the
increasing number of vehicles that would be around the area at the start and
end of term, which would need to be managed.
In response to an enquiry from the
Chair regarding the roof design and why that had been changed, the Land Owner
explained that it was due to style and associated costings.
ORDERED that the application be
Deferred for the following reasons:
To
allow the applicant to provide details which were agreeable to the planning and
highways officers in relation to the provision of adequate parking and
servicing.
22/0064/COU Use as an E-Gaming Centre (sui generis), internal and
external alterations including a replacement shopfront and use of
pedestrianised area to front as café terrace at Unit 5, Captain Cook Square,
Middlesbrough TS1 5UB for Mr E Ford
The Development
Control Manager advised that the above application had been
identified as requiring a site visit by Members of the
Planning and Development Committee.
Accordingly, a site visit had been
held on the morning prior to the meeting.
Full details of the planning
application and the plan status were outlined in the report. The report contained a detailed analysis of
the application and analysed relevant policies from the National Planning
Policy Framework and the Local Development Framework.
The Development Control Manager
advised that planning permission was sought for the change of use of a vacant retail
premises within the town centre’s primary shopping frontage area to an E-gaming
use with café and bar and to use an external area to the front of the premises
as an outdoor seating area.
It was explained that the proposed use was a town
centre use and was appropriate in principle within the town centre, although
local plan policy defined the area as being primary shopping frontage which was
aimed at providing the nucleus of retailing within the town centre. Policy advised there should be no more than
15% non-retailing uses within the Primary Shopping Frontage areas of the town
centre, and the last assessment indicated the non-retailing uses within the PSF
to be 15.7%. Whilst the proposal would
add to the non-retailing uses, it provided a notable leisure destination within
the town centre, adding new uses to the town centre offer which would improve
vitality and viability of the town centre as a result. It was set away from the core area of
Linthorpe Road on the fringe of the PSF area and would therefore not create a
break between different sections of the core retailing uses.
Members heard that the proposal represented a
sustainable and positive re-use of the premises which would attract new
footfall to the town centre and thereby have a positive impact on the vitality
and viability of the town centre. The
proposal would result in the retention and re-occupation of a large unit within
the Captain Cook Square area and would provide a notable leisure destination
within that part of the town centre.
Members were advised that no objections had been
received in relation to the proposal and that the application was recommended
for approval subject to conditions. An
additional condition would be attached to require the Applicant to agree
barrier design with the Planning department.
A Member queried whether the scheme and
E-gaming involved any aspect of gambling.
In response, the Development Control Manager advised that that was not
the case.
A Member made reference to the proposed opening
hours and the inclusion of a bar on the premises, and queried whether any age
restrictions would be put in place. In
response, the Development Control Manager advised that that would be a matter
for Licensing and not imposed from a Planning perspective. The Project Manager for the redevelopment of
Captain Cook Square explained that projects such as the one under consideration
tended to come with their own security and strict protocols attached. It was explained that, as landlord for the
unit, the Council would insist that those be adhered to; age restrictions would
be considered.
A short discussion ensued in relation to
addictive behaviours; consideration was given as to the potential management of
customers in that regard.
ORDERED that the application be Approved
on Condition for the reasons set out in the report.
Supporting documents: