Minutes:
The Executive Member for Finance and Governance and Director of Finance submitted a report for the Executive’s consideration. The report sought approval for the proposals to progress the development of the community centre provision within Nunthorpe ward.
Middlesbrough Council had committed to funding the development of a community centre within Nunthorpe Ward and had identified £900k from the Towns Fund to support the development of the
The Council received interest from separate organisations proposing a community centre at two separate locations. Location 1 being next to the new medical centre, and location 2 being at Nunthorpe & Marton Playing Field Association.
A bidding process was developed in Autumn 2021 in order to identify the most appropriate organisation to design, build and manage the community centre. The process was a two stage bidding process in which initial expressions of interest were submitted, with further refinement at stage 2. The deadline for submissions at stage 2 was 17th December 2021.
The bidding process was independently evaluated by external stakeholders, along with Middlesbrough Council staff, and a conclusion was reached regarding a successful bidder. This however was challenged and further scrutiny was undertaken concerning the building cost detail. As a result the successful bid was subject to scrutiny from the Council’s Quantity surveyor and it was determined there were issues with the build costs. The same scrutiny was provided to the second bid which was deemed acceptable.
On review of the process undertaken the Councils section 151 officer concluded that whilst the process had sought to be as flexible as possible it had not been clear from the outset in regard to key parameters. The process had focussed primarily on building management, rather than design and build, and as such the scrutiny on design and build was undertaken towards the latter part of the evaluation and was not articulated at the outset. This was therefore challengeable.
As a result of the section 151 officer review it was concluded the process be paused and reconsidered in terms of approach.
A revised approach has now been identified which removes a central bidding process and seeks to resolve the key issue of location, by engagement with the community. The revised process will also involve the council managing the build phase, and during the build phase a process will be undertaken to appoint an organisation to run the community facility once built.
OPTIONS
The alternative
course of action was to re-run the bidding exercise with clearly defined
parameters from the outset, however this was not recommended for the following
reasons:
·
Community
organisations have already expended significant time and resource in the
bidding exercise
·
The
expectation for a community organisation to manage a £1million build is
significant, the risk is high for the Town fund resource and as such it is
appropriate for the council to manage the construction to mitigate risks in
this area.
·
Tension
within the community and within community groups would be heightened through
running this exercise, the council has a responsibility to assist with
community relations and following discussion at Nunthorpe Parish council,
community views have been taken on board.
ORDERED
1. That Executive agree to the following
proposed plan to develop the Community centre at Nunthorpe Consult the
community on which of the two available locations that is the site 3 next to
the GP surgery or the current site of the NMPFA building the community would
prefer a community centre to be located. The residents of Nunthorpe will be
engaged specifically on their preference regarding the location of the
community centre and not the historic supporters or proposed management options
associated currently associated with those sites. The consultation exercise
will be managed by the council and will outline two locations from which ward
residents will select a preference.
2. That Executive agree the Consultation
process will run for a fixed period of 6 weeks
3. That Executive agree that following the
outcome of the consultation the council will manage the community centre
development at the preferred site
4. That Executive agree that during the build
a process will be progressed to select a community organisation to manage the
new community asset.
5. That executive approve an additional £100k
from council capital resources due to increased construction costs, once all
other grant funds are exhausted.
REASONS
Within this project,
location is the key factor. Once the location has been determined and agreed,
the build and management of the centre can follow due process. The community
should be involved and consulted on the location as the community would utilise
the centre. Once the location is determined the council will oversee the
development phase, during which a process can be twin tracked to agree an
appropriate organisation to manage the facility in the long term. This option
should minimise demands on community organisations, and ensure the outcome
delivered is the one the majority of ward residents support.
Supporting documents: