The Panel will receive the annual presentation on the Council’s Flood Risk Management arrangements.
RECOMMENDATION: that the Panel determines whether further information is required.
Minutes:
The Panel received a presentation
from the Public Rights of Way Officer on the topic of Flood Risk
Management. As a result of the Pitt
Review in 2007, the Scrutiny Panel was required to receive an annual summary of
actions taken locally and review works carried out, to manage flood risk.
Middlesbrough’s drainage system
was extensive and complex in nature comprising open and culverted watercourses
and a surface water/combined sewerage system.
Flooding could come from a variety of sources including surface water
run off, ordinary watercourses, surcharging sewers and road gullies.
Surface water flooding occurred
when intense rainfall, often of short duration, was unable to permeate into the
ground or enter drainage systems quickly enough, resulting in ponding or
overland flows. This could cause
considerable problems in urban areas.
During periods of heavy rainfall, standing water could accumulate even
if the road gullies were in good working order. Some gullies could not drain the water away
fast enough and therefore would surcharge during periods of intense
rainfall. Such intense periods of
rainfall often short in duration, and once over, the gully would usually drain
away the water without needing any attention.
Areas susceptible to surface water flooding had been identified by the
Environment Agency (EA) and were shown on a map of Middlesbrough.
Middlesbrough Council worked with
Northumbrian Water Limited (NWL) to carry out strategic studies. The strategic studies highlighted and
prioritised the areas of greatest risk from combined flooding within each of
the catchment areas. Middlesbrough was
covered by several catchment areas and each area would have a two stage study
undertaken. Stage 1 focused on the
collection, collation, analysis and prioritisation of information to identify
areas of High Risk from Flooding. Stage
2 focused on identifying opportunities within the top three or four high risk
areas to reduce or prevent flooding. The
Environment Agency also contributed to this work.
A strategic study of
Middlesbrough East, which included some of Redcar and Cleveland had been
undertaken. Stage 1 was completed in
2018 and ten flood risk areas were identified.
Three or four of those areas were taken to a Stage 2 study which was
completed in 2021. Some of the issues
were for the NWL network and others related to surface water flooding. When an area was identified for a scheme it
was added to the EA’s Forward Work Programme for funding. If a scheme was to address surface water this
would be eligible for EA funding.
Flood Defence Grant in Aid
(FDGiA): the EA’s Medium Term Plan was a rolling list of schemes which were
refreshed annually and were funded from Government funding allocation. The funding set by the Government was for
six years and the current funding would run from 2021/2022 to 2026/2027. Councils could put forward schemes of areas
susceptible to surface water flooding, with an indication of how many areas
might get flooded. Then carry out
studies and modelling would be carried out to justify whether to take it
further or whether it was not merited.
On a basic map it might look as though ten properties could be protected
from flooding, but following modelling this figure could potentially
reduce.
Following a recent refresh of the
EA’s Medium Term Plan, eleven potential scheme areas were included that could
protect 636 Middlesbrough homes.
Further details of two current
schemes: Saltersgill Fields and Ormesby High Street were provided.
Construction of the Saltersgill
Fields Scheme started in 2019 and was completed in 2021. The finished scheme was larger than
originally planned and involved the creation of ponds and scrapes between
Saltersgill Road and the allotments, and a bund around the open space between
the allotments and Marton Road. It was
envisaged that around 306 properties were now better protected from
flooding. Additional benefits were
realised as part of the scheme which included the provision of a number of
surfaced footpaths, one of which provided a shortcut to a nearby school. The site was also protected from vehicle
trespass.
Work was currently being
undertaken on the Outline Business Case which for the Ormesby High Street
Scheme which was due to be completed in early January 2023. A second surface water flow from the fields
had been identified and as such the scope of the scheme was expanded. The scheme could involve the creation of a
bund within the National Trust land and so further discussions with the
National Trust were taking place. The
scheme looked to capture overland flows from the Farm Land to the south of the
National Trust property. Potential flood
risk from the culvert under the High Street was identified and improvements had
been made by the EA to the trash screen to prevent obstructions to flow.
The EA had also completed a major
scheme on Marton West Beck that had started in summer 2020 and completed
earlier this year. The scheme had better
protected around 500 homes and businesses.
The trash screen at Albert Park had been improved and extended, with new
flood walls and a surface water storage area installed. New flood walls had also been added at
Borough Road. A new drainage system had
been built and a surface water storage area had also been created in Acklam
behind Teesside Crematorium.
It was highlighted that the water
storage area behind the Crematorium had been improved with wildflowers and
trees planted. The Officer explained
that additional funding was provided for increasing biodiversity alongside
flood management schemes.
The Ormesby Beck Restoration
Scheme began in early August 2022 and was due to be completed by the end of the
year. The scheme would remove the
existing tidal structure which was often over topped by high tides as well as
the screen near to the Navigation Public House.
The grills from the structures would be kept to reuse at a different
location at a later date.
In addition to flood prevention
schemes the Council continued to investigate the highway drainage system, which
had not previously been recorded or mapped, to increase knowledge of the system
and the interactions with sewers and watercourses. The Council could then repair and cleanse the
system where required.
The Council also worked with
Developers to ensure that Sustainable Drainage (SuDs) techniques were included
in all major developments.
In January 2022, Gully Smart, an
asset management software programme was purchased. The aim was to enable both a proactive and
reactive response to tackling flood risk and help with the management of the
highway drainage network. The Panel
received a demonstration of the main features of the software programme at the
meeting.
The Council was starting to build
up a knowledge bank of watercourse locations and resolve some long standing
issues. All roads with gullies had
been surveyed and silt level tests had been carried out. It was noted that silt would block gullies
whereas water could still pass through a build up of fallen leaves. Information was inputted by the Rights of
Way Officer or the surveying personnel.
It was anticipated that there would eventually be link to Firmstep to
enable members of the public to report issues directly.
Members voiced concerns in
relation to the Council’s tree planting programme and whether it was a sensible
policy to plant trees along the roadside.
The Officer confirmed that he was consulted by Area Care and could
advise not to plant trees near culverts.
In addition, he was consulted on any new developments or planning
permissions to ensure that allowance was made for urban creep – where grass was
being replaced by concrete.
The Chair thanked the Officer for
his attendance and presentation.
AGREED that the information provided was received and noted.
Post meeting it was confirmed that the Council currently owned two Gully Suckers and had one permanent gully crew. One machine was kept as a spare to cover times when the main vehicle was being repaired/serviced. The service tended to be responsive and the work with Gully Smart would enable specific areas of concern to be targeted with routine maintenance on those gullies that required regular cleansing.
Supporting documents: