The Head of Planning will be in attendance to give an overview of Enforcement of Planning Conditions.
RECOMMENDATION: that the Panel determine whether further information is required.
Minutes:
The Head of Planning and the
Development Control Manager were in attendance to provide information in
relation to Enforcement of Planning Conditions.
National Planning Policy
Framework (NPPF) paragraph 55 stated that local planning authorities should
consider whether otherwise unacceptable development could be made acceptable through the use of conditions. Middlesbrough Council, as the local planning
authority, tried to issue decisions with as few conditions as possible. There were usually a minimum of two
conditions which were: a standard time limit for commencing a development; and that it should be
built in accordance with the plans.
NPPF paragraph 56 also specified
six tests to ensure that planning conditions should be kept to a minimum and
only imposed where they were:
1. necessary;
2. relevant to planning;
3. relevant to
the development to be permitted;
4. enforceable;
5. precise; and
6. reasonable
in all other respects.
Achieving this was not easy and
one of the reasons why efforts were made to minimise the number of conditions.
Types of planning condition included:
• Standard
time limit condition for commencement of development.
• Details and
drawings subject to which the planning permission was granted.
• Pre-commencement
conditions.
• Pre-occupancy
or other stage conditions.
• Conditions
relating to post occupancy monitoring and management.
Pre-commencement conditions could include details of the materials to be used, landscaping and operation. The local planning authority would try to negotiate these with the Developer so that the plans submitted were approved as soon as possible. Post occupancy could include a noise condition or the replacement of any landscaping if plants died off within so many years.
Conditions could not be used to:
• Unreasonably
impact on the deliverability of a development.
• Reserve
outline application details.
• Require
development to be carried out in its entirety.
• Require
compliance with other regulatory requirements.
• Require
land to be given up.
• Require
payment of money or other considerations.
With regard to
enforcement, it was emphasised that this was discretionary. The local planning authority could decide
whether to take action or not.
A breach of planning control was
defined in section 171A of the Town and Country Planning Act 1990 as:
• The
carrying out of development without the required planning permission; or
• Failing to
comply with any condition or limitation subject to which planning permission has been granted.
The Council had to decide whether it was in the public
interest and proportionate to take action,
particularly if there was a breach of something that planning permission would
have been granted for anyway. For
example, issuing a Section 125 notice for untidy land – the Council could not
ask for the reparation to be of a higher standard than the other properties in
the surrounding area – it had to be equivalent to the rest of the area.
However, effective enforcement was important to:
• Tackle
breaches of planning control which would otherwise have an unacceptable impact on the amenity of
the area.
• Maintain
the integrity of the decision-making process.
• Help ensure
that public acceptance of the decision making-process
was maintained.
In most cases, development became immune from enforcement if
no action was taken:
• Within 4
years of substantial completion for a breach of planning control consisting of operational development.
• Within 4
years for an unauthorised change of use to a single dwelling house.
• Within 10
years for any other breach of planning control (essentially other changes of use).
The 4 year time limit did not apply
if enforcement action had already been taken and there was another breach. Further action could be taken. Also where somebody
deliberately hid what they had done and the planning authority was not aware of
it. The Government changed the ruling so
that the time limit for enforcement was 4 years from the breach.
Enforcement action that could be taken included:
• No formal
action.
• Retrospective
planning application.
• Planning
contravention notice.
• Enforcement
notice.
• Planning
enforcement order.
• Stop
notice.
• Temporary stop notice.
• Breach of
condition notice.
• Injunction.
There were currently
approximately 380 open enforcement cases in Middlesbrough but only 19 were for
breach of condition. During 2022 there had
been approximately 220 new cases which equated to 15 to 20 cases per
month. At the present time there were
more cases coming in than the Authority could deal with. There was one Enforcement Officer in post and
a second post was vacant. The Council prioritised
the cases in line with time limits and also where they
were having a significant impact on residents’ amenity.
The process for taking
enforcement action was to identify the breach.
The Council would usually notified by members
of the public or Councillors. The
breach would then be investigated. If
there was photographic evidence and clearly no breach, then the case could be
closed straightaway. If there was a
breach, the details were logged on the system and prioritised.
The Council would determine what
action was required. So
if a developer built a house in the wrong place, that breach would be enforced
and the building would have to be demolished and rebuilt. However, for more minor infringements – such
as a window being slightly in the wrong position – enforcement would probably
not be taken. The Council would always
try to negotiate to resolve the problem.
This could take a number of months and the
Council had to allow a reasonable length of time for the person who had made
the breach to respond.
If resolution was not found,
formal action would commence with the issuing of a Section 33 notice or a
Planning Contravention Notice (PCN). It
was highlighted that enforcement action could only be taken against the landowner,
not the applicant or the developer. If
the notice was not complied with, court action could be taken. Once a notice was served it could be
appealed and whilst an appeal was live any work on site that was taking place
could continue. If the appeal was
upheld, there would be a notice period for the landowner to comply. If the landowner failed to comply the final
recourse was to go to the Court for an injunction.
The enforcement process could
take a couple of years and potentially there was a cost to the Council. Where there was a breach of a planning
condition, there was no right of appeal, and in that circumstance the Council
could move more quickly.
It was queried whether applicants
with a poor track record on previous developments could be identified at Planning
Committee if a subsequent planning application was submitted. The Officer commented that this might be
considered in the Government’s new Levelling-Up and Regeneration Bill.
With regard to
planning enforcements in conservation areas, it was highlighted that these
areas were regularly surveyed. If
Members had concerns about particular properties, they
were invited to contact the planning department to check whether enforcement
action was being taken.
It was clarified that a new Local
Plan would not be approved until after the Elections in May 2023 but there was
no impact the timeframe for the Plan to be adopted by the end of 2024.
Members raised several examples
of developments that had started but not been completed and the sites had been
left to deteriorate and become unsightly.
One option was to issue a Completion Notice, so that if the development
was not completed then the planning permission was extinguished. However, this could potentially reduce the
value of the site and did not always achieve the aim of improving it. The Council could also consider tidying up a
site itself and then putting the charge for the work back on the
developer.
The issue of nutrient neutrality
was raised which was slowing down the planning process. The local planning authority was bound to
assess the impact that developments had on the river tees and ensure that
mitigation was in place to enable work to go ahead.
AGREED that the information was received and noted.