Issue details

Fountain Court Refurbishment Phase Two Works

The report to Executive on 5th October 2021 approved the £7m budget required to refurbish and fit out Fountain Court ahead of its occupation by Council staff This report provides an update to Executive on the project’s progress and seeks delegated approval for the phase two contract award to be given to the Director of Regeneration and Culture, Richard Horniman and Director of Finance, Ian Wright.

Decision type: Key

Reason Key: Expenditure > £250,000;

Decision status: Recommendations Approved

Wards affected: Central;

Notice of proposed decision first published: 02/02/2022

Anticipated restriction: Public  -

Decision due: 8 Mar 2022 by Executive

Lead member: Executive Member for Environment, Executive Member for Regeneration

Lead director: Director of Regeneration and Culture

Contact: Steve Fletcher, Head of Development Email: Steve_Fletcher@middlesbrough.gov.uk.

Agenda items