Venue: Council Chamber
Contact: Chris Lunn / Georgina Moore
No. | Item | |||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Declarations of Interest Minutes:
|
||||||||||||||||
Minutes - Executive - 14 February 2022 PDF 432 KB Minutes: The
minutes of the Executive meeting held on 14 February 2022 were submitted and
approved as a correct record. |
||||||||||||||||
SUSPENSION OF COUNCIL PROCEDURE RULE NO 5 - ORDER OF BUSINESS ORDERED that, in accordance with Council Procedure Rule No 5, the committee agreed to vary the order of business ORDERED that the following reports be considered as shown: |
||||||||||||||||
Children's Services Improvement Programme: Update Report PDF 415 KB Additional documents:
Minutes: The Deputy Mayor and Executive Member for
Children’s Services and the Executive Director of Children’s Services submitted
a report for the Executive’s consideration. The purpose of the report was to provide
information on the progress made against the Children’s Services Improvement
Plan, with particular reference to the findings of Middlesbrough’s Ofsted
Monitoring Visit in December 2021. Ofsted had carried out a Monitoring Visit to
Children’s Services on 14 and 15 December 2021. The letter summarises the findings
of the monitoring visit (published on 31 January 2022) was attached to the submitted
report (see Background Paper 3). The visit had focused on work with: ·
Children
in Need ·
Children
in Need of Protection ·
The
Public Law outline process - a formal process of work carried out to prevent
work with children being escalated into court. The findings and evaluation of progress were
outlined in the submitted report, the Council’s strengths were detailed at
paragraphs 6 to 15 and areas for development were included at paragraphs 16 to
23. In terms of next steps, the improvement plan
would be revised to reflect the areas for development highlighted by the
Monitoring Visit and there would be a determined focus on moving the quality of
practice. At least two more monitoring visits were
planned to take place, the first of which would be in March 2022, followed by
one in June 2022. The March visit would focus on court work, permanence (which
was a significant factor in the Council receiving its inadequate grading in
January 2020) and looked after children.
In the autumn, Ofsted planned to consult with
the Council in respect of its readiness for a full inspection to determine
whether there should be another monitoring visit, with a full inspection likely
to be at the end of 2022 or early 2023. Although moving out of intervention as
soon as possible seemed positive, the view of the leadership team was that by
waiting an additional few months the Council could gain a higher Ofsted grading
which would stand the authority in good stead going forward. The Multi-Agency Improvement Board met on a six
weekly basis and would continue to do so, at least up until the full
inspection. A board development session, focusing on systems leadership across all
agencies working with children, was planned for April/May 2022. OPTIONS The other
potential decisions that had not been recommended included: The
Executive could have chosen not to formally note the report but that would have
meant that the improvements to services for Middlesbrough’s most vulnerable
children were not formally recognised.
ORDERED 1. That the progress made to improve outcomes for
Middlesbrough’s vulnerable children, as set out in our Children’s Services
Improvement Plan 2020/2023, be noted. 2. That the effect of the work on showing ‘Middlesbrough
Children that they Matter’ be noted. REASON To ensure
that Members were fully briefed. |
||||||||||||||||
2022/23 Transport and Infrastructure Capital Programme PDF 318 KB Additional documents:
Minutes: The Executive Member for Regeneration and the
Director of Regeneration and Culture submitted a report for the Executive’s
consideration. The purpose of the report was to seek approval to allocate funding
to develop and deliver transport and infrastructure improvements. Middlesbrough Council received Local Transport
Plan (LTP) funding from the Department for Transport (DfT)
via Tees Valley Combined Authority (TVCA) to undertake maintenance and improvement
works on the Council’s transport network. The projects within the proposed programme had
been identified from the Council’s ‘Future Year Scheme’ list - a compiled table
of all known requirements and suggestions received, which were ranked for their
suitability against a set criteria. That then formed the priority basis and was
dependent upon external funding criteria, statutory obligations and other
implications. The maintenance schemes were based on asset
condition rating systems and allocation of resources work to address ‘worst
first’ was used. That was rationalised on the basis of public safety and asset
longevity priorities (such as ensuring that structures were safe), ensuring the
Council was addressing the areas of the network in most need of resolving. The Council also received specific allocations
through competitive grant programmes and awards that were provided to deliver
prescribed pieces of work, which were dependent upon national/regional
criteria. Any awards for such projects by-passed the scoring criteria, although
that may be used to identify the most suitable candidates, and could be awarded
throughout the year. The proposals
within the submitted report included all known awarded allocations at time of
approval, but those could be subject to change. The full funding allocations used to identify
the projects/programmes were detailed in Appendix 2 of the submitted report. OPTIONS The other
potential decisions that had not been recommended included: 1. Do nothing - that was not recommended as it would not have
allowed the Council to allocate funding and make the necessary arrangements in
advance of receipt of the allocations. The delivery of infrastructure
improvements required prudent planning, and co-ordination, so approvals in a
timely manner were pivotal to ensuring a successful delivery programme. 2. Re-assessing the project proposals - that was not
recommended, as they had been identified using a scoring matrix to ensure best
allocation of resources. Any changes would have deviated from the process, and
added delays to progressing. ORDERED That the
allocation of funding to develop and deliver infrastructure improvements, as
outlined within the report, be approved. REASON It
planned allow prudent allocation of funding to ensure that the Council was not
only working toward its ambitions and objectives, but was allocating resources
to ensure statutory requirements placed upon the Council as the Highway
Authority, ‘to ensure the safe and expeditious movement of people and goods on
its network’ were met. The allocations that were being proposed were based on ensuring a balance between maintaining existing asset, and making improvements to the accessibility of the current network/alternate modes of transport enhancements. That balance was crucial in order to ensure the safety of the infrastructure, and to assist ... view the full minutes text for item 21/110 |
||||||||||||||||
Fountain Court Refurbishment - Phase Two Works PDF 535 KB Minutes: The Executive Member for Regeneration and the
Director of Regeneration and Culture submitted a report for the Executive’s
consideration. The purpose of the report was to provide an update on the project’s
progress and seek delegated approval for the phase two contract award. Following the purchase of Fountain Court in
spring 2021, a lot of work had been undertaken to ensure the building would
meet the Council’s requirements to be a modern, collaborative place to
work. The report, which had been
submitted to the Executive on 5 October 2021, approved the £7m budget required
to refurbish and fit out Fountain Court ahead of its occupation by Council
staff. Following survey and design work, in October
2021, Overbury Plc were appointed by Middlesbrough Council to carry out the
phase one demolition and strip out of Fountain Court. The phase one works commenced in November
2021 and had removed walls, old kitchens, WCs and mechanical and electrical
services ready for the phase two refurbishment and fit out works. The phase one contract also included the
creation of larger window openings ready for new windows to be installed, as
the current windows were nearing the end of their life. Most of the new windows would be floor to
ceiling height, which planned to significantly improve natural light and the
building’s internal and external appearance.
Moreover, they would be opening windows, which planned to improve the
building’s ventilation. The phase one
strip out works was completed on 18 February 2022. The phase two work was originally intended to
be delivered through the phase one contractors, Overbury. Overbury had submitted its phase two tender
to the Council at the beginning of December 2021. The tender return was in sections, the first
being the installation of all Mechanical and Electrical (M&E) works and the
second covering the builders work to refurbish the building pre-furniture
install. The M&E tender return was within the target
costs set out in the scope of the work, however, the builders work was
significantly over the allocated budget.
The Council offered some value engineering in an attempt to bring the
cost down, albeit that was not enough to achieve the saving and establish best
value for the work. As such, the Council issued a new set of tender
documents to five contractors on 31 January 2022 and their tenders had been
returned on 7 March 2022. The
contractors had been selected based on their specialism and track records. That was for the builders work only and
management of the lowest M&E contractor from the December 2021 tender
return. After completion of the phase one work, a
security firm would be on site to safeguard the building until the main
contractor started work on site in April. The completion date for the phase two work
would be confirmed through the tender process but was targeted for the end of
August 2022, with the furniture install and ICT fit out taking place in early
September, ready for occupation. The timetable for ... view the full minutes text for item 21/111 |
||||||||||||||||
Additional documents: Minutes: The Adult Social Care and Services Scrutiny
Panel had undertaken a review of The Recruitment and Retention of Staff within
Adult Social Care. A copy of the full report was attached. The scrutiny panel had made 6 recommendations
upon which a response was sought from the relevant service area. The Executive
Member for Adult Health and Public Protection, ICT and Digital Inclusion and
the Director of Adult Social Care and Health Integration submitted a service
response to the recommendations of the Adult Social Care and Services Scrutiny
Panel. A copy of the Action Plan was attached. The Chair of the Adult Social Care and Services
Scrutiny Panel presented the final report to the Executive. The Mayor (on
behalf of the Executive Member for Adult Health and Public Protection, ICT and
Digital Inclusion) presented the service response. ORDERED 1. That the content of the Adult Social Care and Services
Scrutiny Panel’s final report, on The Recruitment and Retention of Staff within
Adult Social Care, be noted. 2. That the Action Plan, developed in response to the scrutiny
panel’s recommendations, be approved. REASON It was a
requirement that Executive formally considered the scrutiny panel's report and
confirmed the service area's response to the panel's accompanying plan. |
||||||||||||||||
Towns Fund - Ward Initiatives PDF 488 KB Additional documents:
Minutes: The
Mayor and the Director of Regeneration and Culture submitted a report for the
Executive’s consideration. The purpose of the report was to seek approval to
deliver the programme of schemes developed as part of
the Towns Fund Ward Initiative Project and for the Council to adopt and
maintain the assets. The
Town Deal Board had approved £1m funding for the project. An online survey of
residents had been supplemented with a process of seeking expressions of
interest from Ward Councillors, to identify local
priorities with community support. Parks, green spaces and play areas had been
found to be the areas requiring greatest investment, which had been reflected
in consultation preferences. Ten
projects had been submitted by Members and those were cross referenced with the
Elected Members Small Scheme (EMSS), to avoid duplication. Projects to the
value of approximately £420k had been identified by Members with the indicative
project costs validated by Environment and Community Services (ECS). Member,
Executive and Mayoral requests had also been identified through discussions
with ECS, Cultural Services and Sports and Leisure. Priorities had been
recorded by the Strategy, Information and Governance Team. Those priorities had
identified a significant list of additional projects/requests, which would meet
the objectives of the Town Deal allocation. 29 potential projects had been
identified, costing over £1.26m. The
long list of projects submitted had been assessed against programme
objectives, eligibility, local impact, deliverability and long-term
liabilities. The recommended list included all of the eligible Member
submissions and equated to the full £1m available from the Towns Fund. The
agreed list was attached at Appendix A1 of the submitted report. Those projects
not prioritised, would be held in reserve, should a
selected scheme not go ahead. Those not currently supported, but held in
reserve, were detailed at Appendix A2. The
proposed programme, for approval, was contained under
paragraph 6 of the submitted report. OPTIONS The other potential decisions that had not been
recommended included: ·
Do nothing - That was not recommended, as it would not have met the
requirements of the Towns Fund or address local issues. ·
Invest the Council’s own resources - The Council did not have adequate
funding to deliver projects on the scale required. ·
Invest less Towns Fund resource - The funding allocated was felt to be a
minimum requirement to make a real and lasting change to Middlesbrough’s
environment. Suggested projects far exceeded the funding available. ORDERED 1.
That it be noted that the business case for the Towns Fund Ward
Initiatives Project had been approved by Middlesbrough’s
Town Deal Board. 2.
That the programme of works developed as part
of the Towns Fund Ward Initiatives Project, as set out in appendix A1, be
approved. 3.
That the assets created by the investment be adopted and maintained by Middlesbrough Council, as appropriate. 4.
That works commence to deliver the programme
as soon as possible, subject to supply chain lead times, local
notifications/consultation and any required planning permissions. 5. That the Director of Regeneration and Culture ... view the full minutes text for item 21/113 |
||||||||||||||||
The decision(s) will come into force after five working days following the day the decision(s) was published unless the decision becomes subject to the call in procedures. |